6,475 TGRERA registered projects are past the completion date committed at registration (as of 2026-07-26). 1,452 are more than three years late.

2,120
1,900
1,005
1,452
ProjectBuilderDistrictCommitted dateStatusBand
Luxurio 75 Residences Shree Kamala Estates Llp Ranga Reddy 31 Dec 2024 PAST DUE D
Sunshine Housing - Commercial Sunshine Housing Ranga Reddy 31 Dec 2024 PAST DUE C
Sahasra S Green Meadows 2 Anumolu Jaswanth Rao Ranga Reddy 31 Dec 2024 PAST DUE D
Aikyaa Block B Samuha Ventures Ranga Reddy 31 Dec 2024 PAST DUE D
Aikyaa Block A Samuha Ventures Ranga Reddy 31 Dec 2024 PAST DUE D
Lotus Grand Lotus Projects Ranga Reddy 31 Dec 2024 PAST DUE C
Lakshmi Ganapathi Developers Lakshmi Ganapathi Developers Ranga Reddy 31 Dec 2024 PAST DUE D
Sunyuga Vista Block A Sunyuga Infra Private Limited Ranga Reddy 31 Dec 2024 PAST DUE C
Sunyuga Vista Block B And Block C Sunyuga Infra Private Limited Ranga Reddy 31 Dec 2024 PAST DUE C
Glr Nest Glr Constructions India Private Limited Ranga Reddy 31 Dec 2024 PAST DUE D
My Home Tridasa My Home Infrastructures Pvt Ltd Ranga Reddy 31 Dec 2024 PAST DUE C
My Home Tridasa My Home Infrastructures Pvt Ltd Ranga Reddy 31 Dec 2024 PAST DUE C
Chatla S Sunshine Resisdency S.v.l.n Builders & Developers Nizamabad 31 Dec 2024 PAST DUE C
Us Residency Uma Shanakr Constructions And Developers Khammam 31 Dec 2024 PAST DUE C
Poojitha Developers Bandi Vishnuvardhan Rao & 2 Others Khammam 31 Dec 2024 PAST DUE D
My Fortune Devi Infra Llp My Fortune Devi Infra Llp Medak 31 Dec 2024 PAST DUE D
Elemental337 Elemental Realty Private Limited Hyderabad 1 Jan 2025 PAST DUE D
Sri Venkteswara Township Venepally Madhavi Hyderabad 1 Jan 2025 PAST DUE D
Northeast Residency Northeast Estates Hyderabad 1 Jan 2025 PAST DUE C
Thirumala Ashok Arcade Thirumala Constructions Medchal-Malkajgiri 1 Jan 2025 PAST DUE C
Sai Kiran Residency Golden Homes Builders And Developers Ranga Reddy 1 Jan 2025 PAST DUE C
Pharma Paradise Nenavath Janya & Others Ranga Reddy 1 Jan 2025 PAST DUE C
Cedar Hills Arpan Realtors And Developers And Ravula Ashok Hyderabad 2 Jan 2025 PAST DUE D
Silver Springs Iv Shathabdhi Townships Pvt Ltd Hyderabad 2 Jan 2025 PAST DUE C
Amrutha Residency Shriven Builders & Developers Jagithyal 2 Jan 2025 PAST DUE D
Poladi Nivas M/S Poladi Constructions Karimnagar 3 Jan 2025 PAST DUE C
P.s.b. Vedha Villas Rep By P. Sathaiah Perla Sathaiah And Others Medak 3 Jan 2025 PAST DUE D
Karan Classic Homes R K Builders And Developers Nirmal 3 Jan 2025 PAST DUE D
Gruhashilpis Sumanjali Gruhashilpi Constructions Private Limited Hyderabad 4 Jan 2025 PAST DUE C
Icon Towers Icon Constructions Medchal-Malkajgiri 4 Jan 2025 PAST DUE C
True Grande Commercial C-Block D And U Realty Ventures Llp Ranga Reddy 4 Jan 2025 PAST DUE D
Siri Sampadha Nilayam Sp Infra And Developers Ranga Reddy 4 Jan 2025 PAST DUE D
Rutuja Project Rutuja Projects Nizamabad 4 Jan 2025 PAST DUE D
Neela Kanteshwara Towers Shiva Balaji Associates Nizamabad 4 Jan 2025 PAST DUE D
Sai Rkr Towers Silver Leaf Developers Nizamabad 4 Jan 2025 PAST DUE C
Surya Homes Surya Homes Peddapalli 4 Jan 2025 PAST DUE D
Perams Aditya Signature Park-3 Ggr India Infra Structure Private Limited Hyderabad 5 Jan 2025 PAST DUE D
Soras Green Woods Block A Sora Builders & Developers Medchal-Malkajgiri 5 Jan 2025 PAST DUE C
Riddhi S Venkat Square Riddhi Infra Estate Llp Ranga Reddy 5 Jan 2025 PAST DUE D
Sunrise Avenues Ii Sundeep Daggubati Hyderabad 6 Jan 2025 PAST DUE C
Samprada Oaks Phase Iii Happy Blooms Infra Private Limited Medchal-Malkajgiri 6 Jan 2025 PAST DUE D
Psr Highway County Psr Real Infra Llp Medchal-Malkajgiri 6 Jan 2025 PAST DUE D
Devarakonda Divine Devarakonda Builders And Developers Medchal-Malkajgiri 6 Jan 2025 PAST DUE C
Aditi Green Elite Block-A Aditi Avenues Ranga Reddy 6 Jan 2025 PAST DUE C
Seven Hills Phase Ii Shaik Saleem Nizamabad 6 Jan 2025 PAST DUE C
Urvis Brundavanam Urvi Developers Adilabad 6 Jan 2025 PAST DUE D
Narayanadri Heights Navya Infra Projects Medchal-Malkajgiri 7 Jan 2025 PAST DUE D
Hill Side Yedma Bharath Reddy & Yedma Yadagiri Reddy Ranga Reddy 7 Jan 2025 PAST DUE C
Sai Urban Nest Vuppala Venkatesh Ranga Reddy 7 Jan 2025 PAST DUE C
Palladium Residency Ireddy Constructions Sangareddy 7 Jan 2025 PAST DUE C
Sr Constructions S.r.constructions Sangareddy 8 Jan 2025 PAST DUE C
Sunrise City Cheekati Venkata Apparao And Others Khammam 8 Jan 2025 PAST DUE C
Nakshatra Abode Gangothri Developers Hyderabad 9 Jan 2025 PAST DUE C
Gruhashilpis Saptapadi Gruhashilpi Constructions Private Limited Hyderabad 9 Jan 2025 PAST DUE C
Peacock Estate Ssl Infra Developers Hyderabad 10 Jan 2025 PAST DUE D
Smart City Phase - Iii Smart City Infra Developers Hyderabad 10 Jan 2025 PAST DUE C
Hastina Saniksha Properties Private Limited Hyderabad 10 Jan 2025 PAST DUE C
Simha Fortune Hari Infra Projects Medchal-Malkajgiri 10 Jan 2025 PAST DUE D
Sri Hari Hara Nilayam Laxmidevamma Tippireddy Ranga Reddy 10 Jan 2025 PAST DUE C
Chaitanya Towers Block-B Sri Chaitanyaram Builders Ranga Reddy 10 Jan 2025 PAST DUE C
My Home Enclave Bandarupalli Srinivasa Rao Khammam 10 Jan 2025 PAST DUE C
Oakridge Paradise Tower - 1 Usha Sri Developers Khammam 10 Jan 2025 PAST DUE C
Varada Anjaneya Nagar 2 Nagubandi Ranganadh Nalgonda 10 Jan 2025 PAST DUE D
Shree Balaji Township Jajula Thirupathaih Nagarkurnool 10 Jan 2025 PAST DUE D
Oxygen County Phase-2 Bhashyam Developer Hyderabad 11 Jan 2025 PAST DUE D
Gvk Skycity Dsr Ssc Builders And Developers Hyderabad 11 Jan 2025 PAST DUE D
Janakiram Apartments Sri Janakiram Builders And Developers Medchal-Malkajgiri 11 Jan 2025 PAST DUE C
Navya Park View S S Constructions Ranga Reddy 11 Jan 2025 PAST DUE B
Srinivasa Residency Shree Maruthi Constructions Ranga Reddy 11 Jan 2025 PAST DUE D
Sri Sai Venkateshwara Nagar Devarakonda Chaitra Sindhu Khammam 11 Jan 2025 PAST DUE C
Sree Venkata Sai Residency Sree Mahalakshmi Projects Khammam 11 Jan 2025 PAST DUE C
Sree Vaasavi Towers Thorana Enterprises Ranga Reddy 12 Jan 2025 PAST DUE C
Sri Kara Developers Sri Kara Developers Warangal Urban 12 Jan 2025 PAST DUE D
Rama Lakshma Nilayam Kvn Innovations And Projects Private Limited Hyderabad 13 Jan 2025 PAST DUE D
Tranquil Nests Shreeven Builders And Developers Llp Hyderabad 13 Jan 2025 PAST DUE B
Sikhara Sr Enclave Avani Infra Medchal-Malkajgiri 13 Jan 2025 PAST DUE C
Sri Kurumurthy Swamy Infra Developers Bongoni Suresh Kumar Siddipet 13 Jan 2025 PAST DUE D
Ashoka Residency Dnr Constructions Medak 13 Jan 2025 PAST DUE D
Srinivasam Sri. Mellacheruvu Koteshwar Rao & Others Suryapet 13 Jan 2025 PAST DUE D
Mango Leaf Ext Kakatiya Infra Projects Private Limited(Opc) Ranga Reddy 16 Jan 2025 PAST DUE D
Dharur Layout Mohammed Arifuddin Hyderabad 17 Jan 2025 PAST DUE D
Amrutha Grand Amrutha Construtions Hyderabad 17 Jan 2025 PAST DUE C
Mythri Infra Ventures Mythri Infra Ventures Hyderabad 17 Jan 2025 PAST DUE D
Madhav Meadows Aishwarya Infra Medchal-Malkajgiri 17 Jan 2025 PAST DUE C
Srija Homes Block A Srijaconstructions Medchal-Malkajgiri 17 Jan 2025 PAST DUE C
Srija Homes Block B Srijaconstructions Medchal-Malkajgiri 17 Jan 2025 PAST DUE C
Ss Sadan Sree Ss Constructions Ranga Reddy 17 Jan 2025 PAST DUE C
Balaji Infra Projects Balaji Infra Projects Sangareddy 17 Jan 2025 PAST DUE C
Icons Comfort Icon Developers Hyderabad 18 Jan 2025 PAST DUE C
Aditya Arcade Aditya Constructions Builders And Developers Medchal-Malkajgiri 18 Jan 2025 PAST DUE C
Lemon Tree Garudainfrarealtors Medchal-Malkajgiri 18 Jan 2025 PAST DUE D
Khyathi Nivas Khyathi Housing Projects Private Limited Ranga Reddy 18 Jan 2025 PAST DUE C
Avana Navatha Homes Warangal Urban 18 Jan 2025 PAST DUE D
Sr Jasmine Sr Builders And Developers Nizamabad 18 Jan 2025 PAST DUE C
Srinivasam Enclave Reddy Satyanarayana Nizamabad 18 Jan 2025 PAST DUE C
Suryanagar Layout Chennoju Raja Brahmam And Other Individuals Mancherial 18 Jan 2025 PAST DUE D
Om Sai Colony Venkatreddy Uppula Nalgonda 18 Jan 2025 PAST DUE D
Gouri Enclave Gouri Madhukar Adilabad 18 Jan 2025 PAST DUE D
Green Parkphase Ii B Khajagesudaraj And Others Mahabubnagar 18 Jan 2025 PAST DUE D
My Home Mangala My Home Constructions Pvt. Ltd. Hyderabad 19 Jan 2025 PAST DUE C

Page 33 of 65 · ← Prev Next →

"Past due" compares today against the completion date committed at registration. Telangana publishes no granted-extension counts or completion status. Derived from public records as of 2026-07-26.

How many Telangana RERA projects are running late?

6,475 TGRERA registered projects are past the completion date committed at registration (as of 2026-07-26). 1,452 are more than three years late.

Shortlisting here? Verify before you pay.

We check title and RERA standing, benchmark the price against registration data, and negotiate with the builder on your side. Free first consultation.