Green Parkphase Ii

PAST DUE 1.5 yrs past committed date

Yes — registered with TGRERA on 18 Jan 2023, with a committed completion date of 18 Jan 2025. It is currently 1.5 years past that date.

D
18 Jan 2025

Health score components

ComponentScoreReading
Timeline adherence33Overdue 1.5 yrs vs the date committed at registration.
Sales / booking momentumn/aUnit inventory not disclosed on the register.
Approval documents55No plan-approval reference found on the TGRERA record.
Legal & enforcement100No litigation or enforcement flagged.
Builder track record45Based on B Khajagesudaraj And Others's portfolio: past-due share, litigation and enforcement across their TGRERA projects.

Confidence: partial. Telangana publishes no progress % or completion status, and unit inventory only for some projects, so missing components are excluded and the rest reweighted. Derived from public TGRERA records as of 2026-07-25.

Registration record

FieldValue
BuilderB Khajagesudaraj And Others (Individual)
TypePlotted · plots
LocationMarikal, Mahabubnagar — 509351
Approving authorityDTCP
Registered on18 Jan 2023
Committed completion18 Jan 2025
Unitsinventory not disclosed
Legal / enforcementNone flagged
Official recordVerify on the TGRERA portal

Is Green Parkphase Ii RERA registered in Telangana?

Yes — registered with TGRERA on 18 Jan 2023, with a committed completion date of 18 Jan 2025. It is currently 1.5 years past that date.

Who is the builder of Green Parkphase Ii?

B Khajagesudaraj And Others. See their full Telangana track record on this site.

Shortlisting here? Verify before you pay.

We check title and RERA standing, benchmark the price against registration data, and negotiate with the builder on your side. Free first consultation.