Sri Chaitanyaram Builders
Sri Chaitanyaram Builders has 11 TGRERA registered projects across Ranga Reddy. 8 are past their committed completion date.
11
8
0
0
Registered projects
| Project | District | Registered | Committed date | Status | Band |
|---|---|---|---|---|---|
| Chaitanya Pride | Ranga Reddy | 13 Sep 2021 | 13 Sep 2024 | PAST DUE | C |
| Chaitanya Towers Block A | Ranga Reddy | 27 Sep 2018 | 27 Sep 2024 | PAST DUE | D |
| Chaitanya Towers Block-B | Ranga Reddy | 10 Jan 2019 | 10 Jan 2025 | PAST DUE | C |
| Chaitanya Icon | Ranga Reddy | 31 Jan 2022 | 31 Jan 2025 | PAST DUE | C |
| Sri Chaitanya Nilayam | Ranga Reddy | 3 Mar 2020 | 3 Mar 2026 | PAST DUE | B |
| Chaitanya Pride | Ranga Reddy | 10 Apr 2023 | 10 Apr 2026 | PAST DUE | C |
| Chaitanya Ruby | Ranga Reddy | 3 Jun 2023 | 3 Jun 2026 | PAST DUE | C |
| Chaitanya Habitat | Ranga Reddy | 10 Aug 2023 | 10 Aug 2026 | DUE SOON | B |
| Chaitanya Enclave | Ranga Reddy | 12 Aug 2021 | 12 Aug 2027 | REGISTERED | B |
| Sri Satya Chaitanya Elite | Ranga Reddy | 18 Apr 2021 | 18 Apr 2027 | REGISTERED | A |
| Chaitanya Avenue | Ranga Reddy | 7 Jul 2020 | 7 Jul 2026 | PAST DUE | B |
Track record derived from public TGRERA records as of 2026-07-25. "Past due" = past the completion date committed at registration; Telangana publishes no granted-extension counts.
How many RERA projects does Sri Chaitanyaram Builders have in Telangana?
Sri Chaitanyaram Builders has 11 TGRERA registered projects across Ranga Reddy. 8 are past their committed completion date.
Does Sri Chaitanyaram Builders have any RERA enforcement in Telangana?
No enforcement action or litigation is flagged on the TGRERA record for their projects.