VerifyRERATelangana · TGRERA
Home/Telangana/Builders/Dnr Constructions

Dnr Constructions

Dnr Constructions has 7 TGRERA registered projects across Sangareddy, Medak. 7 are past their committed completion date.

7
7
0
0

Registered projects

ProjectDistrictRegisteredCommitted dateStatusBand
Ashoka Residency Medak 13 Jan 2021 13 Jan 2025 PAST DUE D
Woodland Residency Medak 4 Feb 2021 2 Feb 2025 PAST DUE C
Harshith Resdiency Medak 2 Feb 2021 2 Feb 2025 PAST DUE C
Dnr Shilpa Residency Medak 25 May 2021 25 May 2025 PAST DUE C
Ashoka Hill Park Medak 8 Jul 2021 8 Jul 2025 PAST DUE C
Ramakrishna Residency Sangareddy 13 Feb 2020 13 Feb 2026 PAST DUE B
Pragathi Residency Sangareddy 28 Feb 2020 28 Feb 2026 PAST DUE B

Track record derived from public TGRERA records as of 2026-07-25. "Past due" = past the completion date committed at registration; Telangana publishes no granted-extension counts.

How many RERA projects does Dnr Constructions have in Telangana?

Dnr Constructions has 7 TGRERA registered projects across Sangareddy, Medak. 7 are past their committed completion date.

Does Dnr Constructions have any RERA enforcement in Telangana?

No enforcement action or litigation is flagged on the TGRERA record for their projects.