6,479 TGRERA registered projects are past the completion date committed at registration (as of 2026-07-27). 1,454 are more than three years late.

2,122
1,899
1,006
1,454
ProjectBuilderDistrictCommitted dateStatusBand
Sree Laxmi Narasimha Residency Vision Construction Ranga Reddy 30 Apr 2025 PAST DUE C
Sree Balaji County-Ii Jbn Infra Developers Ranga Reddy 30 Apr 2025 PAST DUE C
Subhiksha Homes Bhavya Sree Developers Ranga Reddy 30 Apr 2025 PAST DUE B
Sri Ayyappa Sairam Residency Sasr Constructions And Sri P Rajashekar Reddy Ranga Reddy 30 Apr 2025 PAST DUE C
Aadhya Arcade Prominent Infra Developers Warangal Urban 30 Apr 2025 PAST DUE C
Uma Maheswara Towers Uma Maheswara Developers Nizamabad 30 Apr 2025 PAST DUE C
Vijayalaxmi Estates Varahi Builders Karimnagar 30 Apr 2025 PAST DUE C
Nagarjuna County Cherukumalli Rukkaiah Bhadradri Kothagudem 30 Apr 2025 PAST DUE B
Unm Aura Unm Lifespaces Private Limited Hyderabad 1 May 2025 PAST DUE C
Anils Chintapatla Anil Kumar Medchal-Malkajgiri 1 May 2025 PAST DUE D
Varahi Nagar Gurram Sai Kiran Reddy And Others Ranga Reddy 1 May 2025 PAST DUE C
Amrutha Valley Warangal Infra Developers Warangal Urban 1 May 2025 PAST DUE C
Kakatiya Vantage Kakatiya Infra Tech Warangal Urban 1 May 2025 PAST DUE C
Gkinfrastructures Gk Infrastructures Warangal Urban 1 May 2025 PAST DUE C
Subhiksha Colony Shaik Javeed And Others Hyderabad 2 May 2025 PAST DUE C
Silpa Raghava Botanica Silpa Raghava Ventures Llp Hyderabad 2 May 2025 PAST DUE C
Sucasa Highlands Sucasa Infra Hyderabad 2 May 2025 PAST DUE C
Abhigna Avasa Abhigna Infra Developers Ranga Reddy 2 May 2025 PAST DUE C
Avantikas Godavari Block 1 Avantikagreens Ranga Reddy 2 May 2025 PAST DUE C
S S Engineers Residency Thara Constructions Karimnagar 2 May 2025 PAST DUE C
Lakshmi Hills Akula Gopikrishna Kamareddy 2 May 2025 PAST DUE C
Orange County Bhagyabhoomi Developers India Private Limited Hyderabad 3 May 2025 PAST DUE C
The Native Vasanthavihar Agro Farms Pvt Ltd Artreum Ventures Llp Prasuha Real Estates Pvt Ltd G Srividya Reddy Hyderabad 3 May 2025 PAST DUE C
Mahaveer Colony Jain Kumar Sanjay Hyderabad 3 May 2025 PAST DUE C
Lake View Apartment Indu Developers Hyderabad 3 May 2025 PAST DUE C
Dream Town Eipl Infra Ventures Ranga Reddy 3 May 2025 PAST DUE C
Tribhuvan Manasri Infrastructure And Developers Pvt Ltd Ranga Reddy 3 May 2025 PAST DUE C
Doctors Colony Mohammad Abdul Hadi And Others Siddipet 3 May 2025 PAST DUE C
Sri Laxmi Ganapathi Developers Bandari Raji Reddy Kamareddy 3 May 2025 PAST DUE C
F3 Infra F3 Infra Adilabad 3 May 2025 PAST DUE C
Sri Sai Venkateshwara Nagar Kiran Komaraneni Khammam 4 May 2025 PAST DUE C
Padmavathi Township - 2 Manugu Alias Manugula Rayamallu And Three Individuals Mancherial 5 May 2025 PAST DUE C
Abhayanjaneya Township Thatikonda Srinivasa Reddy Suryapet 5 May 2025 PAST DUE C
Sai Brindavan Colony Mukku Venu Gopal Vikarabad 5 May 2025 PAST DUE C
Westerene County Bhashyam Developer Hyderabad 6 May 2025 PAST DUE C
Green Metros Tulasi Vanam Ph-2 Greenmetro Infratech & Projects Private Limited Hyderabad 6 May 2025 PAST DUE C
Valvekar Residency Bhagyashree Constructions Hyderabad 6 May 2025 PAST DUE C
Anjanadari Enclave Aman Teja Infra Medchal-Malkajgiri 6 May 2025 PAST DUE C
Vishwasya Stellarview Vew Infra Projects Medchal-Malkajgiri 6 May 2025 PAST DUE C
Nova Sunrise Dpr Infra Projects Private Limited Ranga Reddy 6 May 2025 PAST DUE C
Jb Towers Syed Ahmed Pasha Khammam 6 May 2025 PAST DUE C
Cloud Heights Cloud9Builders Khammam 6 May 2025 PAST DUE C
Essen Marvella Essen Infra Group Hyderabad 7 May 2025 PAST DUE C
Sark Green Scapes Sark Projects (India) Private Limited Ranga Reddy 7 May 2025 PAST DUE C
Gayathri Nilayam B V R Housing Projects Ranga Reddy 7 May 2025 PAST DUE C
The Meadow Dance Phase-Ii Total Evnvironment Bulding Systems Privtae Limited BANGALORE RURAL 7 May 2025 PAST DUE C
Glentree Green Hills M/S Glentree Homes Llp Hyderabad 8 May 2025 PAST DUE C
Tulip Apartments Block C Starlite Spintech Limited Hyderabad 8 May 2025 PAST DUE C
Pnr Enclave Laxmaiah Karlapudi Khammam 8 May 2025 PAST DUE C
Smart County Balguri Manga Reddy And Chendra Shekar Gadangi Hyderabad 9 May 2025 PAST DUE C
Fortune Retreat Phase - I Green City Sreenivasa Estates Llp Hyderabad 9 May 2025 PAST DUE C
Lake Breeze Seshadri Rudraksh Megacorp Private Limited Hyderabad 9 May 2025 PAST DUE C
Lake Breeze Neeladri Rudraksh Megacorp Private Limited Hyderabad 9 May 2025 PAST DUE C
Saffron Elite Trishala Infrastructure Pvt Ltd Hyderabad 9 May 2025 PAST DUE C
Gateway Manors Uniton Infra Private Limited Ranga Reddy 9 May 2025 PAST DUE C
Sai Chandra Hill Ridge Apurva Constructions Ranga Reddy 9 May 2025 PAST DUE C
Pearl Residency S R Constructions Hyderabad 10 May 2025 PAST DUE B
Coral Residency S R Constructions Hyderabad 10 May 2025 PAST DUE C
Jain Sadguru Images Capital Park Jain Sadguru Constructions Llp Hyderabad 10 May 2025 PAST DUE C
Padmavathi Classic Homes Mathrubhumi Infra Medchal-Malkajgiri 10 May 2025 PAST DUE C
Balwanth Reddy Classic Enclave Mathrubhumi Infra Medchal-Malkajgiri 10 May 2025 PAST DUE C
Jms Chaitanya Jms Constructions Medchal-Malkajgiri 10 May 2025 PAST DUE C
Hill County B Obul Reddy Ranga Reddy 10 May 2025 PAST DUE C
Mahagiri Township Phase-Iii Extension Siri Laxmi Sai Construction Private Limited Ranga Reddy 10 May 2025 PAST DUE C
Sri Sai Manohara Towers Sri Sai Constructions Karimnagar 10 May 2025 PAST DUE C
Bhavagnyas Infinity Towers Bhavagnya Infra Projects Hyderabad 11 May 2025 PAST DUE C
Sri Soudha Advik Avenue Sri Soudha Builders Hyderabad 11 May 2025 PAST DUE C
Sri Lakshmi Green City Chinni Raj Kumar And Chinni Krishna Rao Khammam 11 May 2025 PAST DUE C
Citadel Developers Citadel Developers Khammam 11 May 2025 PAST DUE C
Nidhi Heights Block A Gak Estates And Projects Hyderabad 12 May 2025 PAST DUE C
Nidhi Heights Block B Gak Estates And Projects Hyderabad 12 May 2025 PAST DUE C
Infocity Marvel Info City Infratech Ranga Reddy 12 May 2025 PAST DUE C
Vasudaika Cosmo Elite Vasudaika Projects Llp Ranga Reddy 12 May 2025 PAST DUE C
Varalaxmi Township Padigela Varalaxmi Kamareddy 12 May 2025 PAST DUE C
Aakar Heights - A Totaram Builders And Developers Llp Hyderabad 13 May 2025 PAST DUE C
Ohana Bliss M/S Ohana Homes Ranga Reddy 13 May 2025 PAST DUE C
Deram City Vs Developers Ranga Reddy 13 May 2025 PAST DUE C
Lakshmi Enclave Bonam Venkata Rangaiah Naidu WEST GODAVARI 13 May 2025 PAST DUE C
Mgts Shrisannidhi Mgts Collective Private Limited Hyderabad 14 May 2025 PAST DUE C
Fortune One Sri Sreenivasa Constructions Hyderabad 14 May 2025 PAST DUE E
S S Developers Surabhi Saidamma And Others Suryapet 14 May 2025 PAST DUE C
Subiksha Towers Subiksha Infra Medchal-Malkajgiri 15 May 2025 PAST DUE C
Sai Vaishnavi Block A Sai Neeraj Constructions Ind Pvt Ltd Medchal-Malkajgiri 15 May 2025 PAST DUE B
Sai Vaishnavi Block B Sai Neeraj Constructions Ind Pvt Ltd Medchal-Malkajgiri 15 May 2025 PAST DUE B
Raghavendra Brundhavanam M/S Rk Infrastructures Medchal-Malkajgiri 15 May 2025 PAST DUE D
Geethasreeheights Kohinoor Infra Ranga Reddy 15 May 2025 PAST DUE C
Veerabhadra Nagar Sri Veerabhadra Swamy Developers Karimnagar 15 May 2025 PAST DUE C
Sri Vengamamba Townsville Bala Saroja Patchava Bhadradri Kothagudem 15 May 2025 PAST DUE C
Kalpavan 2 Sri Laxmi Venkataramana Constructions Hyderabad 16 May 2025 PAST DUE C
Aakriti Esta D Block Aakriti Constructions And Developers Private Limited Hyderabad 16 May 2025 PAST DUE B
Durga Laxmi Shubh Sri Durga Developers Hyderabad 16 May 2025 PAST DUE C
Landspace Elite Landspace Group Housing Projects Medchal-Malkajgiri 16 May 2025 PAST DUE C
Ayyapa Nagar New City Developers Medchal-Malkajgiri 16 May 2025 PAST DUE C
Neela Sreenidhi Projects Medchal-Malkajgiri 16 May 2025 PAST DUE C
Amr Sunshine Homes Saranya Constructions Ranga Reddy 16 May 2025 PAST DUE C
Sri Varenya Venture Sri Avenue Infra Developers Warangal Urban 16 May 2025 PAST DUE C
Shree Paada Towers Shreepaada Constructions Nizamabad 16 May 2025 PAST DUE C
Abhima Enclave G Santhosh Kumar And Other Individual Mahabubnagar 16 May 2025 PAST DUE C
Gita Serene Block-A Makuta Developers And Infrastructures Private Limited Hyderabad 17 May 2025 PAST DUE C
Gita Serene Block-B Makuta Developers And Infrastructures Private Limited Hyderabad 17 May 2025 PAST DUE C

Page 40 of 65 · ← Prev Next →

"Past due" compares today against the completion date committed at registration. Telangana publishes no granted-extension counts or completion status. Derived from public records as of 2026-07-27.

How many Telangana RERA projects are running late?

6,479 TGRERA registered projects are past the completion date committed at registration (as of 2026-07-27). 1,454 are more than three years late.

Shortlisting here? Verify before you pay.

We check title and RERA standing, benchmark the price against registration data, and negotiate with the builder on your side. Free first consultation.