Siri Laxmi Sai Construction Private Limited

Siri Laxmi Sai Construction Private Limited has 8 TGRERA registered projects across Ranga Reddy. 7 are past their committed completion date.

8
7
0
0

Registered projects

ProjectDistrictRegisteredCommitted dateStatusBand
Mahagiri Daimond City Ranga Reddy 24 Sep 2021 24 Sep 2023 STALLED D
Mahagiri Diamond City Ranga Reddy 7 Apr 2022 4 Jul 2024 STALLED D
Mahagiri Golden Hills Ranga Reddy 2 Aug 2021 2 Aug 2024 PAST DUE D
Vihari New City Ranga Reddy 31 Dec 2022 31 Dec 2024 PAST DUE D
Mahagiri Golden City New Ranga Reddy 31 Mar 2023 31 Mar 2025 PAST DUE C
Mahagiri Township Phase-Iii Extension Ranga Reddy 10 May 2020 10 May 2025 PAST DUE C
Mahagiri Diamond City Ranga Reddy 22 Oct 2020 22 Oct 2025 PAST DUE B
Vihari New City-Ii Ranga Reddy 6 Dec 2024 6 Dec 2026 REGISTERED A

Track record derived from public TGRERA records as of 2026-07-25. "Past due" = past the completion date committed at registration; Telangana publishes no granted-extension counts.

How many RERA projects does Siri Laxmi Sai Construction Private Limited have in Telangana?

Siri Laxmi Sai Construction Private Limited has 8 TGRERA registered projects across Ranga Reddy. 7 are past their committed completion date.

Does Siri Laxmi Sai Construction Private Limited have any RERA enforcement in Telangana?

No enforcement action or litigation is flagged on the TGRERA record for their projects.