Apporva ‘A is registered with TNRERA as TN/01/Building/028/2019 (Building registration, 2019). The promoter is , who has 552 projects on the TNRERA register. The RERA-committed completion date is 31 Mar 2020 — that date has now passed. Committed dates are legally binding under RERA.
Latest quarterly progress filing
Caution: the RERA-committed completion date has passed, and the last quarterly filing reported 85% physical completion. Ask the builder for the current status and updated timeline before paying anything.
Stage, as filed: Block/Tower, Floor wise completed in 2nd attached in 3rd & 4th Floor , Separate Sheet Flooring progress in 1st Floor
Source: the project's Quarterly Progress Report filed with TNRERA (as on the quarter shown; may not reflect current status).
Apartment sizes (carpet area)
RERA carpet areas for this project, read from the filed area statement — the real usable floor area, excluding balcony and common space.
Carpet areas range from 756 to 3,983 sq.ft (median 829 sq.ft) across 3 units.
Machine-read from the filed carpet-area statement. Normalised to sq.ft from sq.m. View the original document filed with TNRERA ↗
About this registration
Project Name: "Apporva ‘A’ Block" - Construction of Block-A – Stilt floor + 4 floors with 72 dwelling units comprised in S.No.447/2 (as per document) and S.No.447/2A as per patta and S.No.447/2B1 (as per document & patta) of Kovoor Village, Sriperumbudur Taluk, Kancheepuram District.
Approval: Renewal of Planning Permission issued by Member-Secretary, CMDA, Chennai-8 vide letter No.EC/C1/17862/2015, dated 30.06.2016. Building License issued by President, Kovoor Village Panchayat vide letter dated BA/90/2012-13
Status on register: Progress of Work as on March 2020
Builder track record:
has 552 projects on the TNRERA register since 2017, with no completion-date extensions on record. See the full record →
Frequently asked
Is Apporva ‘A RERA registered?
Yes — registered with TNRERA as TN/01/Building/028/2019 in 2019. Always quote this number when dealing with the builder; unregistered projects cannot legally be marketed or sold in Tamil Nadu.
When will Apporva ‘A be completed?
The RERA-committed completion date is 31 Mar 2020. No deadline extensions are on record.
Who is the builder of Apporva ‘A?
, with 552 projects on the TNRERA register and no completion-date extensions on record.
← All Sriperumbudur–Oragadam projects and market data
Source documents on TNRERA
These are the government's own filed documents for this project. We link them directly — verify anything on this page against them.
Shortlisting here? Verify before you pay.
We check title and RERA standing, benchmark the price against registration data, and negotiate with the builder on your side. Free first consultation.