Construction for 2 Blocks of Block A & B – Stilt floor + 4 floors

TN/01/Building/0059/2018PAST COMMITTED DATE

Construction for 2 Blocks of Block A & B – Stilt floor + 4 floors is registered with TNRERA as TN/01/Building/0059/2018 (Building registration, 2018). The promoter is M/s. Urban Tree Infrastructure Pvt. Ltd., who has 4 projects on the TNRERA register. The RERA-committed completion date is 30 Jun 2020 — that date has now passed. Committed dates are legally binding under RERA.

19 Feb 2018
30 Jun 2020
96
0

Latest quarterly progress filing — 31st December 2019

Stage, as filed: Floor wise 2.

Source: the project's Quarterly Progress Report filed with TNRERA (as on the quarter shown; may not reflect current status).

Apartment sizes (carpet area)

RERA carpet areas for this project, read from the filed area statement — the real usable floor area, excluding balcony and common space.

ConfigurationCarpet area (sq.ft)Units
2BHK75648
3BHK97032

Machine-read from the filed carpet-area statement. Normalised to sq.ft from sq.m. View the original document filed with TNRERA ↗

About this registration

Construction for 2 Blocks of Block A & B – Stilt floor + 4 floors with 48 dwelling units each (Total 96 dwelling units) at S.No.105/3A, 106/11, Rajiv Nagar, Noombal Village, Thiruverkadu Municipality, Ambattur Taluk, Tiruvallur District.

Approval: Approved by Member-Secretary, CMDA – PP No.B/Spl.Bldg/169 A to J / 2017 in letter No.BC1/18393/2014 dated 6.6.17 and the Commissioner, Tiruverkadu Municipality Building License No.949/2017 in letter No.191/2017 dated 20.

Status on register: Progress of Work as on December 2019

Planning permission for this project was issued by CMDA (read from the approval document on the TNRERA register).

Builder track record: M/s. Urban Tree Infrastructure Pvt. Ltd.

M/s. Urban Tree Infrastructure Pvt. Ltd. has 4 projects on the TNRERA register since 2017, with no completion-date extensions on record. See the full record →

Frequently asked

Is Construction for 2 Blocks of Block A & B – Stilt floor + 4 floors RERA registered?

Yes — registered with TNRERA as TN/01/Building/0059/2018 in 2018. Always quote this number when dealing with the builder; unregistered projects cannot legally be marketed or sold in Tamil Nadu.

When will Construction for 2 Blocks of Block A & B – Stilt floor + 4 floors be completed?

The RERA-committed completion date is 30 Jun 2020. No deadline extensions are on record.

Who is the builder of Construction for 2 Blocks of Block A & B – Stilt floor + 4 floors?

M/s. Urban Tree Infrastructure Pvt. Ltd., with 4 projects on the TNRERA register and no completion-date extensions on record.

← All Ambattur–Avadi Belt projects and market data

Source documents on TNRERA

These are the government's own filed documents for this project. We link them directly — verify anything on this page against them.

Shortlisting here? Verify before you pay.

We check title and RERA standing, benchmark the price against registration data, and negotiate with the builder on your side. Free first consultation.