M/s. Urban Tree Infrastructure Pvt. Ltd. has 4 projects on the TNRERA register since 2017 — 236 units/plots in total, concentrated in Kancheepuram District, OMR Corridor, Ambattur–Avadi Belt. 0 completion-deadline extensions are recorded across their projects, and 4 projects are past their committed completion dates on the register. All figures from TNRERA public records.

4
2017
236
0

Builder Performance Dashboard

Computed from TNRERA register entries only — every metric's method is stated below it. Register status can lag reality; treat as one research input.

50%
0%
2
19 mo
1.7 mo

Marked completed: share of their 4 registrations whose register status reads “Completed” (TN-wide: 81%) — note this naturally tracks portfolio age; a builder whose projects are mostly recent will show a low share without it meaning delay. Deadline extended: share with a recorded completion-date extension or “Extension given” status (TN-wide: 0%). Past date, not completed: projects whose RERA-committed date has passed without a “Completed” status, of 4 with a known committed date. Avg committed timeline: mean months between registration and committed completion, where both dates are on record. Approval → RERA: median months between the planning-approval document date (OCR'd from the filed approval) and RERA registration, across 1 projects where both dates are readable.

All TNRERA registrations by M/s. Urban Tree Infrastructure Pvt. Ltd.

ProjectRERA No.LocalityYearCommitted byUnits
Grove-IV TN/01/Layout/0015/2020 Porur Belt 2020 30 Jun 2020 DONE
Construction for 2 Blocks of Block A & B – Stilt floor + 4 floors TN/01/Building/0059/2018 Ambattur–Avadi Belt 2018 30 Jun 2020 96
Construction for Block C to F of Stilt Floor+ 4 Floors Residential with total 140 Dwelling TN/02/Building/0118/2017 Kancheepuram District 2017 31 Dec 2019 140 DONE
Construction of 3 Blocks for Residence – N, P & R, with Stilt Flo… TN/01/Building/0243/2017 OMR Corridor 2017 31 Mar 2019

How to read this record

Does M/s. Urban Tree Infrastructure Pvt. Ltd. deliver on time?

No completion-deadline extensions are recorded across their 4 registered projects — a clean register on this measure.

Where does M/s. Urban Tree Infrastructure Pvt. Ltd. build?

Their registrations concentrate in Kancheepuram District, OMR Corridor, Ambattur–Avadi Belt, Porur Belt.