Home/Builders/THE EXECUTIVE ENGINEER & ADO

THE EXECUTIVE ENGINEER & ADO

THE EXECUTIVE ENGINEER & ADO has 40 projects on the TNRERA register since 2018 — 5,067 units/plots in total, concentrated in Ambattur–Avadi Belt, Madurai District, Central Chennai. 0 completion-deadline extensions are recorded across their projects, and 19 projects are past their committed completion dates on the register. All figures from TNRERA public records.

40
2018
5,067
0

Builder Performance Dashboard

Computed from TNRERA register entries only — every metric's method is stated below it. Register status can lag reality; treat as one research input.

48%
0%
14
22 mo

Marked completed: share of their 40 registrations whose register status reads “Completed” (TN-wide: 81%) — note this naturally tracks portfolio age; a builder whose projects are mostly recent will show a low share without it meaning delay. Deadline extended: share with a recorded completion-date extension or “Extension given” status (TN-wide: 0%). Past date, not completed: projects whose RERA-committed date has passed without a “Completed” status, of 19 with a known committed date. Avg committed timeline: mean months between registration and committed completion, where both dates are on record.

All TNRERA registrations by THE EXECUTIVE ENGINEER & ADO

ProjectRERA No.LocalityYearCommitted byUnits
Layout of house sites TN/02/Layout/1257/2023 Ambattur–Avadi Belt 2023 23 DONE
Layout of house sites with HIG 19 Plots and LIG 10 Plots (Total 29 Plots) + 1 Shop site co TN/02/Layout/02361/2023 Ambattur–Avadi Belt 2023 29 DONE
Construction of Registration of Stilt Floor + 14 Floors TN/16/Building/0253/2022 Tiruchirappalli District 2022
Revised Layout of house sites comprised in S.Nos.2/4, 2/5, 2/6, 11/1 of Nallingapettai Agr TN/30/Layout/5433/2022 Krishnagiri District 2022 DONE
Ellis Nagar TN/20/Layout/9343/2022 Madurai District 2022 46 DONE
Construction of Basement Floor + Ground Floor + 6 Floors TN/10/Building/0033/2021 Erode District 2021 28 Oct 2025 36
Construction of Stilt Floor Part / Ground Floor Part + 3 Floors Sho… TN/02/Building/0048/2021 Ambattur–Avadi Belt 2021 31 Mar 2021
Construction of Stilt Floor + 9 Floor TN/29/Building/0075/2021 Ambattur–Avadi Belt 2021 30 Jun 2024 72
Construction of Combined Extended Basement Floor for Block-A & B. B… TN/29/Building/0250/2021 Ambattur–Avadi Belt 2021 31 Dec 2023 240
Layout of house sites comprised in S.No.43/2 of Thathaneri Village, Madurai North Taluk, M TN/20/Layout/0059/2021 Madurai District 2021 DONE
Layout of house sites TN/20/Layout/0069/2021 Madurai District 2021 38 DONE
Layout of house sites comprised in S.Nos.40/1B, 40/2 & 40/4 of Thattaneri Village, Madurai TN/20/Layout/0072/2021 Madurai District 2021 DONE
Residential Layout with 18 Plots + 1 Shop site + 1 Own use comprised in S.Nos.24/9 part TN/20/Layout/0073/2021 Madurai District 2021 18 DONE
Layout of house sites comprised in S.Nos.72/1, 72/2A, 72/3A & 72/5A, T.S.Nos.17/2 & 17/21, TN/07/Layout/0319/2021 Salem District 2021 DONE
Construction of Group Development of 3 Blocks of Block - A & B: Sti… TN/02/Building/0047/2020 Ambattur–Avadi Belt 2020 30 Apr 2021 160
Construction of Group Developnment of 3 Blocks of Stilt Floor + 4 F… TN/02/Building/0048/2020 Ambattur–Avadi Belt 2020 30 Apr 2021 148
Construction of Stilt Floor + 7 Floors TN/29/Building/0065/2020 Ambattur–Avadi Belt 2020 49 DONE
Construction of 30 HIG Flats at Ellis Nagar, Madurai TN/20/Building/0129/2020 Madurai District 2020 30
Hosur Phase-III TN/30/Building/0306/2020 Krishnagiri District 2020 6 Sep 2022
Hosur NH Scheme, Phase-XIX TN/30/Building/0315/2020 2020 30 Sep 2022 70
Construction of Slum Tenements of Stilt Floor + 5 Floors TN/29/Building/0334/2020 Chennai District 2020 26 May 2022 60
Construction of Group Development of 6 Blocks – Block-1: Stilt Fl… TN/29/Building/0337/2020 Ambattur–Avadi Belt 2020 31 Dec 2022 205
Construction of Stilt Floor + 4 Floors TN/29/Building/0356/2020 Central Chennai 2020 30 Nov 2022
Construction of Block-1: Stilt Floor + 5 Floors TN/29/Building/0378/2020 Ambattur–Avadi Belt 2020 31 Dec 2022 90 DONE
Construction of Block - I & II of Stilt Floor + 5 Floors TN/11/Building/0391/2020 Coimbatore District 2020 30 Sep 2022 60
Construction of Stilt Floor + 5 Floors TN/19/Building/0402/2020 Pudukkottai District 2020 15
Construction of Stilt Floor + 9 Floors TN/29/Building/0427/2020 Ambattur–Avadi Belt 2020 108 DONE
Construction of Periyar Nagar - Pocket I - Block-A of GF + 3F TN/10/Building/0464/2020 Erode District 2020 10 Jan 2022
Construction of Stilt Floor + 4 Floors TN/29/Building/0476/2020 Ambattur–Avadi Belt 2020 16
Layout of house sites comprised in T.S.No.310/3 of (Suthamalli Village, S.No.772/3), Block TN/26/Layout/0130/2020 Tirunvelveli District 2020 DONE
Hosur NH Scheme, Phase-XIX TN/30/Layout/0156/2020 2020 30 Sep 2022 265
Mullur Satellite Town Scheme TN/19/Layout/0170/2020 Pudukkottai District 2020 1,603
Layout of House Sites with HIG – 216 Plots, MIG - 489 Plots & EWS - 609 Plots Total - 1314 TN/16/Layout/0185/2020 Tiruchirappalli District 2020 1,314
Construction of High rise residential Group development of 2 Blocks… TN/29/Building/0123/2019 Ambattur–Avadi Belt 2019 260 DONE
Construction of Stilt Floor + 4 Floors TN/29/Building/0130/2019 Ambattur–Avadi Belt 2019 30 Mar 2020 40 DONE
Construction of Stilt Floor + 6 Floors TN/29/Building/0173/2019 Ambattur–Avadi Belt 2019 31 Aug 2021 60 DONE
Construction of Stilt Floor + 4 Floors TN/29/Building/0178/2019 OMR Corridor 2019 30 Apr 2020 DONE
Construction of Stilt floor + 11 floors TN/29/Building/0184/2019 Ambattur–Avadi Belt 2019 DONE
Construction of Stilt floor + 4 floors TN/29/Building/0215/2018 Central Chennai 2018 20 Jun 2019 12 DONE
Construction of EWS Type – 1 (Type Design No.57/16) Plot Nos. 2 t… TN/13/Building/0291/2018 Thanjavur District 2018

How to read this record

Does THE EXECUTIVE ENGINEER & ADO deliver on time?

No completion-deadline extensions are recorded across their 40 registered projects — a clean register on this measure.

Where does THE EXECUTIVE ENGINEER & ADO build?

Their registrations concentrate in Ambattur–Avadi Belt, Madurai District, Central Chennai, Krishnagiri District, Pudukkottai District.

Get the full dossier (PDF)

A downloadable, builder-level RERA dossier with this builder featured — the health score explained, the builder's complete track record against the Tamil Nadu benchmark, a carpet-area annexure, the full portfolio, a chronology and links to the government source documents.

Download the dossier →