Uma Maheswara Colony I
PAST DUE 2.6 yrs past committed date
Yes — registered with TGRERA on 1 Jan 2022, with a committed completion date of 1 Jan 2024. It is currently 2.6 years past that date.
Health score components
| Component | Score | Reading |
|---|---|---|
| Timeline adherence | 14 | Overdue 2.6 yrs vs the date committed at registration. |
| Sales / booking momentum | n/a | Unit inventory not disclosed on the register. |
| Approval documents | 100 | Local plan-approval reference is on the TGRERA record. |
| Legal & enforcement | 100 | No litigation or enforcement flagged. |
| Builder track record | 45 | Based on Kummari Venkata Ramulu's portfolio: past-due share, litigation and enforcement across their TGRERA projects. |
Confidence: partial. Telangana publishes no progress % or completion status, and unit inventory only for some projects, so missing components are excluded and the rest reweighted. Derived from public TGRERA records as of 2026-07-25.
Registration record
| Field | Value |
|---|---|
| Builder | Kummari Venkata Ramulu (Individual) |
| Type | Plotted · plots |
| Location | Mahabubnagar — 509375 |
| Approving authority | DTCP |
| Registered on | 1 Jan 2022 |
| Committed completion | 1 Jan 2024 |
| Units | inventory not disclosed |
| Legal / enforcement | None flagged |
| Official record | Verify on the TGRERA portal |
Is Uma Maheswara Colony I RERA registered in Telangana?
Yes — registered with TGRERA on 1 Jan 2022, with a committed completion date of 1 Jan 2024. It is currently 2.6 years past that date.
Who is the builder of Uma Maheswara Colony I?
Kummari Venkata Ramulu. See their full Telangana track record on this site.
Shortlisting here? Verify before you pay.
We check title and RERA standing, benchmark the price against registration data, and negotiate with the builder on your side. Free first consultation.