Techpark
STALLED 3.7 yrs past committed date
Yes — registered with TGRERA on 7 Sep 2020, with a committed completion date of 31 Oct 2022. It is currently 3.7 years past that date.
Health score components
| Component | Score | Reading |
|---|---|---|
| Timeline adherence | 16 | Registered project years past its committed date with no reported bookings. |
| Sales / booking momentum | n/a | Unit inventory not disclosed on the register. |
| Approval documents | 100 | Local plan-approval reference is on the TGRERA record. |
| Legal & enforcement | 100 | No litigation or enforcement flagged. |
| Builder track record | 59 | Based on Inspire Infra's portfolio: past-due share, litigation and enforcement across their TGRERA projects. |
Confidence: partial. Telangana publishes no progress % or completion status, and unit inventory only for some projects, so missing components are excluded and the rest reweighted. Derived from public TGRERA records as of 2026-07-25.
Registration record
| Field | Value |
|---|---|
| Builder | Inspire Infra (Company) |
| Type | Commercial · commercial · G1; G2; G4; 101 LAND OWNER; 102 LAND OWNER; 103LAND OWNER; 104; 201; 202 LAND OWNER; 203; 204 LAND OWNER; 301 LAND OWNER; 302; 303; 304 LAND OWNER; 401 LAND OWNER; 402; 403; 404 |
| Location | Gandipet, Ranga Reddy — 500089 |
| Approving authority | HMDA |
| Registered on | 7 Sep 2020 |
| Committed completion | 31 Oct 2022 |
| Units | inventory not disclosed |
| Legal / enforcement | None flagged |
| Official record | Verify on the TGRERA portal |
Is Techpark RERA registered in Telangana?
Yes — registered with TGRERA on 7 Sep 2020, with a committed completion date of 31 Oct 2022. It is currently 3.7 years past that date.
Who is the builder of Techpark?
Inspire Infra. See their full Telangana track record on this site.
Shortlisting here? Verify before you pay.
We check title and RERA standing, benchmark the price against registration data, and negotiate with the builder on your side. Free first consultation.