Sri Vasanth Vihar
PAST DUE 1.7 yrs past committed date
Yes — registered with TGRERA on 21 Nov 2022, with a committed completion date of 21 Nov 2024. It is currently 1.7 years past that date.
Health score components
| Component | Score | Reading |
|---|---|---|
| Timeline adherence | 30 | Overdue 1.7 yrs vs the date committed at registration. |
| Sales / booking momentum | n/a | Unit inventory not disclosed on the register. |
| Approval documents | 55 | No plan-approval reference found on the TGRERA record. |
| Legal & enforcement | 100 | No litigation or enforcement flagged. |
| Builder track record | 45 | Based on Enjamuri Linga Reddy And Others's portfolio: past-due share, litigation and enforcement across their TGRERA projects. |
Confidence: partial. Telangana publishes no progress % or completion status, and unit inventory only for some projects, so missing components are excluded and the rest reweighted. Derived from public TGRERA records as of 2026-07-25.
Registration record
| Field | Value |
|---|---|
| Builder | Enjamuri Linga Reddy And Others (Company) |
| Type | Plotted · plots |
| Location | Hyderabad — 500033 |
| Approving authority | DTCP |
| Registered on | 21 Nov 2022 |
| Committed completion | 21 Nov 2024 |
| Units | inventory not disclosed |
| Legal / enforcement | None flagged |
| Official record | Verify on the TGRERA portal |
Is Sri Vasanth Vihar RERA registered in Telangana?
Yes — registered with TGRERA on 21 Nov 2022, with a committed completion date of 21 Nov 2024. It is currently 1.7 years past that date.
Who is the builder of Sri Vasanth Vihar?
Enjamuri Linga Reddy And Others. See their full Telangana track record on this site.
Shortlisting here? Verify before you pay.
We check title and RERA standing, benchmark the price against registration data, and negotiate with the builder on your side. Free first consultation.