Sri Sai Housing Corporation
STALLED 5.6 yrs past committed date
Yes — registered with TGRERA on 12 Dec 2018, with a committed completion date of 21 Dec 2020. It is currently 5.6 years past that date.
Health score components
| Component | Score | Reading |
|---|---|---|
| Timeline adherence | 16 | Registered project years past its committed date with no reported bookings. |
| Sales / booking momentum | n/a | Unit inventory not disclosed on the register. |
| Approval documents | 55 | No plan-approval reference found on the TGRERA record. |
| Legal & enforcement | 100 | No litigation or enforcement flagged. |
| Builder track record | 45 | Based on Sri Sai Housing Corporation's portfolio: past-due share, litigation and enforcement across their TGRERA projects. |
Confidence: partial. Telangana publishes no progress % or completion status, and unit inventory only for some projects, so missing components are excluded and the rest reweighted. Derived from public TGRERA records as of 2026-07-25.
Registration record
| Field | Value |
|---|---|
| Builder | Sri Sai Housing Corporation (Company) |
| Type | Plotted · plots |
| Location | KHAIRTABAD, Hyderabad — 500082 |
| Approving authority | HMDA |
| Registered on | 12 Dec 2018 |
| Committed completion | 21 Dec 2020 |
| Units | inventory not disclosed |
| Legal / enforcement | None flagged |
| Official record | Verify on the TGRERA portal |
Is Sri Sai Housing Corporation RERA registered in Telangana?
Yes — registered with TGRERA on 12 Dec 2018, with a committed completion date of 21 Dec 2020. It is currently 5.6 years past that date.
Who is the builder of Sri Sai Housing Corporation?
Sri Sai Housing Corporation. See their full Telangana track record on this site.
Shortlisting here? Verify before you pay.
We check title and RERA standing, benchmark the price against registration data, and negotiate with the builder on your side. Free first consultation.