Sri Nivasam
PAST DUE 0.6 yrs past committed date
Yes — registered with TGRERA on 30 Jul 2020, with a committed completion date of 31 Dec 2025. It is currently 0.6 years past that date.
Health score components
| Component | Score | Reading |
|---|---|---|
| Timeline adherence | 50 | Overdue 0.6 yrs vs the date committed at registration. |
| Sales / booking momentum | n/a | Unit inventory not disclosed on the register. |
| Approval documents | 100 | Local plan-approval reference is on the TGRERA record. |
| Legal & enforcement | 100 | No litigation or enforcement flagged. |
| Builder track record | 53 | Based on Vasavi Constructions's portfolio: past-due share, litigation and enforcement across their TGRERA projects. |
Confidence: partial. Telangana publishes no progress % or completion status, and unit inventory only for some projects, so missing components are excluded and the rest reweighted. Derived from public TGRERA records as of 2026-07-25.
Registration record
| Field | Value |
|---|---|
| Builder | Vasavi Constructions (Company) |
| Type | Residential · apartment · 2 BHK G4; 3 BHK G7; 2 BHK G11; 2 BHK G8; 2 BHK G12 and G13; 2 BHK G6; 2 BHK G14 and G15; 3 BHK G16; 2 BHK G3 and G5; 3 BHK G9 and G10; 2 BHK G1; 2 BHK 111; 2 BHK 114 and 115; 2 BHK 112 and 113; 3 BHK 116; 3 BHK 101; 2 BHK 108; 2 BHK 102 and 104; 2 BHK 103 and 105; 2 BHK 106; 3 BHK 107; 3 BHK 109 and 110; 3 BHK 209 and 210; 2 BHK 211; 2 BHK 208; 2 BHK 214 and 215; 3 BHK 216; 3 BHK 201; 2 BHK 202 and 204; 2 BHK 203 and 205; 2 BHK 206; 3 BHK 207; 2 BHK 212 and 213; 3 BHK 301; 2 BHK 306; 3 BHK 307; 3 BHK 309 and 310; 2 BHK 311; 2 BHK 312 and 313; 2 BHK 308; 2 BHK 303 and 305; 2 BHK 314 and 316; 3 BHK 316; 2 BHK 302 and 304; 3 BHK 401; 2 BHK 402 and 404; 2 BHK 406; 3 BHK 407; 3 BHK 409 and 410; 2 BHK 411; 2 BHK 414 and 415; 2 BHK 403 and 405; 2 BHK 408; 2 BHK 412 and 413; 3 BHK 416; 3 BHK 501; 2 BHK 502 and 504; 2 BHK 503 and 505; 2 BHK 506; 3 BHK 507; 2 BHK 508; 3 BHK 509 and 510; 2 BHK 511; 2 BHK 514 and 515; 3 BHK 516; 2 BHK 512 and 513 |
| Location | Medipally, Medchal-Malkajgiri — 500098 |
| Approving authority | HMDA |
| Registered on | 30 Jul 2020 |
| Committed completion | 31 Dec 2025 |
| Units | inventory not disclosed |
| Legal / enforcement | None flagged |
| Official record | Verify on the TGRERA portal |
Is Sri Nivasam RERA registered in Telangana?
Yes — registered with TGRERA on 30 Jul 2020, with a committed completion date of 31 Dec 2025. It is currently 0.6 years past that date.
Who is the builder of Sri Nivasam?
Vasavi Constructions. See their full Telangana track record on this site.