Shree Shakti Pinacle

PAST DUE 2.5 yrs past committed date

Yes — registered with TGRERA on 1 Feb 2018, with a committed completion date of 1 Feb 2024. It is currently 2.5 years past that date.

D
1 Feb 2024

Health score components

ComponentScoreReading
Timeline adherence15Overdue 2.5 yrs vs the date committed at registration.
Sales / booking momentumn/aUnit inventory not disclosed on the register.
Approval documents55No plan-approval reference found on the TGRERA record.
Legal & enforcement100No litigation or enforcement flagged.
Builder track record45Based on Sree Shakti Developers's portfolio: past-due share, litigation and enforcement across their TGRERA projects.

Confidence: partial. Telangana publishes no progress % or completion status, and unit inventory only for some projects, so missing components are excluded and the rest reweighted. Derived from public TGRERA records as of 2026-07-25.

Registration record

FieldValue
BuilderSree Shakti Developers (Company)
TypeResidential · apartment · 101 3BHK; 102 2BHK; 103 3BHK; 201 3BHK; 202 2BHK; 203 3BHK; 301 3BHK; 302 2BHK; 303 3BHK; 401 3BHK; 402 2BHK; 403 3BHK; 501 3BHK; 502 2BHK; 503 3BHK
LocationBachupally, Medchal-Malkajgiri — 500090
Approving authorityGHMC
Registered on1 Feb 2018
Committed completion1 Feb 2024
Unitsinventory not disclosed
Legal / enforcementNone flagged
Official recordVerify on the TGRERA portal

Is Shree Shakti Pinacle RERA registered in Telangana?

Yes — registered with TGRERA on 1 Feb 2018, with a committed completion date of 1 Feb 2024. It is currently 2.5 years past that date.

Who is the builder of Shree Shakti Pinacle?

Sree Shakti Developers. See their full Telangana track record on this site.

Shortlisting here? Verify before you pay.

We check title and RERA standing, benchmark the price against registration data, and negotiate with the builder on your side. Free first consultation.