Lotus Park
STALLED 2 yrs past committed date
Yes — registered with TGRERA on 9 Jul 2021, with a committed completion date of 9 Jul 2024. It is currently 2 years past that date.
Health score components
| Component | Score | Reading |
|---|---|---|
| Timeline adherence | 16 | Registered project years past its committed date with no reported bookings. |
| Sales / booking momentum | n/a | Unit inventory not disclosed on the register. |
| Approval documents | 55 | No plan-approval reference found on the TGRERA record. |
| Legal & enforcement | 100 | No litigation or enforcement flagged. |
| Builder track record | 45 | Based on Rayaan Constructions's portfolio: past-due share, litigation and enforcement across their TGRERA projects. |
Confidence: partial. Telangana publishes no progress % or completion status, and unit inventory only for some projects, so missing components are excluded and the rest reweighted. Derived from public TGRERA records as of 2026-07-25.
Registration record
| Field | Value |
|---|---|
| Builder | Rayaan Constructions (Company) |
| Type | Residential · apartment · 101 3BHK; 102 2BHK; 103 3BHK; 201 3BHK; 202 2BHK; 203 3BHK; 301 3BHK; 302 2BHK; 303 3BHK; 401 3BHK; 402 2BHK; 403 3BHK; 501 3BHK; 502 2BHK; 503 3BHK |
| Location | Kukatpally, Medchal-Malkajgiri — 500072 |
| Approving authority | DTCP |
| Registered on | 9 Jul 2021 |
| Committed completion | 9 Jul 2024 |
| Units | inventory not disclosed |
| Legal / enforcement | None flagged |
| Official record | Verify on the TGRERA portal |
Is Lotus Park RERA registered in Telangana?
Yes — registered with TGRERA on 9 Jul 2021, with a committed completion date of 9 Jul 2024. It is currently 2 years past that date.
Who is the builder of Lotus Park?
Rayaan Constructions. See their full Telangana track record on this site.