STALLED 2.7 yrs past committed date

Yes — registered with TGRERA on 5 Jan 2021, with a committed completion date of 30 Oct 2023. It is currently 2.7 years past that date.

C
30 Oct 2023

Health score components

ComponentScoreReading
Timeline adherence16Registered project years past its committed date with no reported bookings.
Sales / booking momentumn/aUnit inventory not disclosed on the register.
Approval documents100Local plan-approval reference is on the TGRERA record.
Legal & enforcement100No litigation or enforcement flagged.
Builder track record45Based on K Ramesh Patel's portfolio: past-due share, litigation and enforcement across their TGRERA projects.

Confidence: partial. Telangana publishes no progress % or completion status, and unit inventory only for some projects, so missing components are excluded and the rest reweighted. Derived from public TGRERA records as of 2026-07-25.

Registration record

FieldValue
BuilderK Ramesh Patel (Company)
TypePlotted · plots
LocationUppal, Medchal-Malkajgiri — 500076
Approving authorityHMDA
Registered on5 Jan 2021
Committed completion30 Oct 2023
Unitsinventory not disclosed
Legal / enforcementNone flagged
Official recordVerify on the TGRERA portal

Is Kramesh And Kkrupakarreddy RERA registered in Telangana?

Yes — registered with TGRERA on 5 Jan 2021, with a committed completion date of 30 Oct 2023. It is currently 2.7 years past that date.

Who is the builder of Kramesh And Kkrupakarreddy?

K Ramesh Patel. See their full Telangana track record on this site.

Shortlisting here? Verify before you pay.

We check title and RERA standing, benchmark the price against registration data, and negotiate with the builder on your side. Free first consultation.