VerifyRERATelangana · TGRERA
Home/Telangana/Hyderabad/Khammam Haritage Phase-3

Khammam Haritage Phase-3

PAST DUE 0.4 yrs past committed date

Yes — registered with TGRERA on 21 Mar 2024, with a committed completion date of 20 Mar 2026. It is currently 0.4 years past that date.

C
20 Mar 2026

Health score components

ComponentScoreReading
Timeline adherence54Overdue 0.4 yrs vs the date committed at registration.
Sales / booking momentumn/aUnit inventory not disclosed on the register.
Approval documents55No plan-approval reference found on the TGRERA record.
Legal & enforcement100No litigation or enforcement flagged.
Builder track record45Based on Aadhaar Builders And Infrastructure Llp's portfolio: past-due share, litigation and enforcement across their TGRERA projects.

Confidence: partial. Telangana publishes no progress % or completion status, and unit inventory only for some projects, so missing components are excluded and the rest reweighted. Derived from public TGRERA records as of 2026-07-25.

Registration record

FieldValue
BuilderAadhaar Builders And Infrastructure Llp (Company)
TypePlotted · plots
LocationHyderabad — 500034
Approving authorityDTCP
Registered on21 Mar 2024
Committed completion20 Mar 2026
Unitsinventory not disclosed
Legal / enforcementNone flagged
Official recordVerify on the TGRERA portal

Is Khammam Haritage Phase-3 RERA registered in Telangana?

Yes — registered with TGRERA on 21 Mar 2024, with a committed completion date of 20 Mar 2026. It is currently 0.4 years past that date.

Who is the builder of Khammam Haritage Phase-3?

Aadhaar Builders And Infrastructure Llp. See their full Telangana track record on this site.

Shortlisting here? Verify before you pay.

We check title and RERA standing, benchmark the price against registration data, and negotiate with the builder on your side. Free first consultation.