Bhuvanam Villas
PAST DUE 0.7 yrs past committed date NEGOTIATION ROOM
Yes — registered with TGRERA on 24 Sep 2021, with a committed completion date of 21 Nov 2025. It is currently 0.7 years past that date.
Health score components
| Component | Score | Reading |
|---|---|---|
| Timeline adherence | 48 | Overdue 0.7 yrs vs the date committed at registration. |
| Sales / booking momentum | 48 | 12% of approved units booked; 14 still available. |
| Approval documents | 100 | Local plan-approval reference is on the TGRERA record. |
| Legal & enforcement | 100 | No litigation or enforcement flagged. |
| Builder track record | 45 | Based on Mark Nirmaan's portfolio: past-due share, litigation and enforcement across their TGRERA projects. |
Confidence: full. Telangana publishes no progress % or completion status, and unit inventory only for some projects, so missing components are excluded and the rest reweighted. Derived from public TGRERA records as of 2026-07-25.
Registration record
| Field | Value |
|---|---|
| Builder | Mark Nirmaan (Company) |
| Type | Residential · apartment · VILLA 4 BHK; VILLA 4BHK |
| Location | Hyderabad — 500029 |
| Approving authority | HMDA |
| Registered on | 24 Sep 2021 |
| Committed completion | 21 Nov 2025 |
| Units | 16 approved · 2 booked · 14 available |
| Legal / enforcement | None flagged |
| Official record | Verify on the TGRERA portal |
Is Bhuvanam Villas RERA registered in Telangana?
Yes — registered with TGRERA on 24 Sep 2021, with a committed completion date of 21 Nov 2025. It is currently 0.7 years past that date.
Who is the builder of Bhuvanam Villas?
Mark Nirmaan. See their full Telangana track record on this site.