STALLED 2.3 yrs past committed date

Yes — registered with TGRERA on 3 Oct 2022, with a committed completion date of 31 Mar 2024. It is currently 2.3 years past that date.

D
31 Mar 2024

Health score components

ComponentScoreReading
Timeline adherence16Registered project years past its committed date with no reported bookings.
Sales / booking momentumn/aUnit inventory not disclosed on the register.
Approval documents55No plan-approval reference found on the TGRERA record.
Legal & enforcement100No litigation or enforcement flagged.
Builder track record63Based on Avani Infra Developers's portfolio: past-due share, litigation and enforcement across their TGRERA projects.

Confidence: partial. Telangana publishes no progress % or completion status, and unit inventory only for some projects, so missing components are excluded and the rest reweighted. Derived from public TGRERA records as of 2026-07-25.

Registration record

FieldValue
BuilderAvani Infra Developers (Company)
TypePlotted · plots
LocationAmberpet, Hyderabad — 500013
Approving authorityHMDA
Registered on3 Oct 2022
Committed completion31 Mar 2024
Unitsinventory not disclosed
Legal / enforcementNone flagged
Official recordVerify on the TGRERA portal

Is Avanis East Lake Avenue Extension RERA registered in Telangana?

Yes — registered with TGRERA on 3 Oct 2022, with a committed completion date of 31 Mar 2024. It is currently 2.3 years past that date.

Who is the builder of Avanis East Lake Avenue Extension?

Avani Infra Developers. See their full Telangana track record on this site.

Shortlisting here? Verify before you pay.

We check title and RERA standing, benchmark the price against registration data, and negotiate with the builder on your side. Free first consultation.