Akshita Golden Breeze Extension-One
PAST DUE 5.8 yrs past committed date
Yes — registered with TGRERA on 11 Jan 2019, with a committed completion date of 30 Sep 2020. It is currently 5.8 years past that date.
Health score components
| Component | Score | Reading |
|---|---|---|
| Timeline adherence | 12 | Overdue 5.8 yrs vs the date committed at registration. |
| Sales / booking momentum | n/a | Unit inventory not disclosed on the register. |
| Approval documents | 55 | No plan-approval reference found on the TGRERA record. |
| Legal & enforcement | 100 | No litigation or enforcement flagged. |
| Builder track record | 45 | Based on Akshita Infra Projects Llp's portfolio: past-due share, litigation and enforcement across their TGRERA projects. |
Confidence: partial. Telangana publishes no progress % or completion status, and unit inventory only for some projects, so missing components are excluded and the rest reweighted. Derived from public TGRERA records as of 2026-07-25.
Registration record
| Field | Value |
|---|---|
| Builder | Akshita Infra Projects Llp (Company) |
| Type | Plotted · plots |
| Location | Ranga Reddy — 500047 |
| Approving authority | HMDA |
| Registered on | 11 Jan 2019 |
| Committed completion | 30 Sep 2020 |
| Units | inventory not disclosed |
| Legal / enforcement | None flagged |
| Official record | Verify on the TGRERA portal |
Is Akshita Golden Breeze Extension-One RERA registered in Telangana?
Yes — registered with TGRERA on 11 Jan 2019, with a committed completion date of 30 Sep 2020. It is currently 5.8 years past that date.
Who is the builder of Akshita Golden Breeze Extension-One?
Akshita Infra Projects Llp. See their full Telangana track record on this site.