Vishnu Developers

Vishnu Developers has 12 TGRERA registered projects across Sangareddy. 5 are past their committed completion date.

12
5
0
0

Registered projects

ProjectDistrictRegisteredCommitted dateStatusBand
Signature One Sangareddy 3 Nov 2021 3 Nov 2024 PAST DUE C
Vihanga Sangareddy 27 Jan 2022 27 Jan 2025 PAST DUE B
The Origin Sangareddy 26 Apr 2022 26 Apr 2025 PAST DUE B
Sankalp Sangareddy 7 Feb 2023 7 Feb 2026 PAST DUE C
The Icon Sangareddy 11 Dec 2025 11 Dec 2028 REGISTERED A
Anvaya Sangareddy 25 Aug 2025 25 Aug 2028 REGISTERED A
Ameya Sangareddy 20 Aug 2025 20 Aug 2028 REGISTERED A
Sahasra Sangareddy 5 Sep 2024 5 Sep 2027 REGISTERED B
Park Way Sangareddy 15 May 2024 15 May 2027 REGISTERED B
Hill Crest Sangareddy 25 Jan 2024 25 Jan 2027 REGISTERED B
Amogha Sangareddy 22 Aug 2023 22 Aug 2026 DUE SOON B
Aspire Sangareddy 15 Jul 2023 15 Jul 2026 PAST DUE C

Track record derived from public TGRERA records as of 2026-07-24. "Past due" = past the completion date committed at registration; Telangana publishes no granted-extension counts.

How many RERA projects does Vishnu Developers have in Telangana?

Vishnu Developers has 12 TGRERA registered projects across Sangareddy. 5 are past their committed completion date.

Does Vishnu Developers have any RERA enforcement in Telangana?

No enforcement action or litigation is flagged on the TGRERA record for their projects.