Surya Constructions has 8 TGRERA registered projects across Medchal-Malkajgiri, Hyderabad, Warangal Urban. 7 are past their committed completion date.
8
7
0
0
Registered projects
| Project | District | Registered | Committed date | Status | Band |
|---|---|---|---|---|---|
| Surya Kuteers Vrushabhadri | Warangal Urban | 29 Oct 2018 | 31 Aug 2020 | STALLED | D |
| Galaxy Towers | Medchal-Malkajgiri | — | 31 Mar 2022 | STALLED | D |
| Surya Land Mark | Hyderabad | 5 Dec 2018 | 5 Dec 2023 | STALLED | D |
| Surya Elite | Hyderabad | — | 16 Jan 2024 | PAST DUE | C |
| Surya Enclave | Hyderabad | 6 May 2021 | 6 May 2024 | STALLED | C |
| Stambadri Enclave | Medchal-Malkajgiri | 8 Oct 2021 | 30 Sep 2024 | PAST DUE | C |
| Galaxy Towers | Medchal-Malkajgiri | 22 Jan 2020 | 22 Jan 2026 | PAST DUE | C |
| Galaxy Towers -Iii | Medchal-Malkajgiri | 19 Aug 2021 | 18 Aug 2027 | REGISTERED | C |
Track record derived from public TGRERA records as of 2026-07-25. "Past due" = past the completion date committed at registration; Telangana publishes no granted-extension counts.
How many RERA projects does Surya Constructions have in Telangana?
Surya Constructions has 8 TGRERA registered projects across Medchal-Malkajgiri, Hyderabad, Warangal Urban. 7 are past their committed completion date.
Does Surya Constructions have any RERA enforcement in Telangana?
No enforcement action or litigation is flagged on the TGRERA record for their projects.