Siri Constructions
Siri Constructions has 8 TGRERA registered projects across Ranga Reddy, Medchal-Malkajgiri, Hyderabad. 7 are past their committed completion date.
8
7
0
0
Registered projects
| Project | District | Registered | Committed date | Status | Band |
|---|---|---|---|---|---|
| Siris Inara | Ranga Reddy | 9 Jan 2019 | 8 Jan 2024 | STALLED | D |
| Narayanadri Residency | Medchal-Malkajgiri | 25 Nov 2021 | 25 Nov 2024 | PAST DUE | D |
| Venkatadri Residency | Medchal-Malkajgiri | 25 Nov 2021 | 25 Nov 2024 | PAST DUE | C |
| Siris Ananda | Ranga Reddy | 6 Mar 2019 | 6 Mar 2025 | PAST DUE | C |
| Siri Nilayam | Medchal-Malkajgiri | 22 Aug 2019 | 22 Aug 2025 | PAST DUE | C |
| Sree Srinivasam | Hyderabad | 15 Feb 2020 | 15 Feb 2026 | PAST DUE | B |
| Siris Damodhar Sadan | Medchal-Malkajgiri | 15 Jun 2023 | 15 Jun 2026 | PAST DUE | C |
| Sri Lakshmi Surya Apartments | Hyderabad | 7 May 2021 | 7 May 2027 | REGISTERED | A |
Track record derived from public TGRERA records as of 2026-07-24. "Past due" = past the completion date committed at registration; Telangana publishes no granted-extension counts.
How many RERA projects does Siri Constructions have in Telangana?
Siri Constructions has 8 TGRERA registered projects across Ranga Reddy, Medchal-Malkajgiri, Hyderabad. 7 are past their committed completion date.
Does Siri Constructions have any RERA enforcement in Telangana?
No enforcement action or litigation is flagged on the TGRERA record for their projects.