Silpa Infratech Limited
Silpa Infratech Limited has 4 TGRERA registered projects across Hyderabad. 4 are past their committed completion date.
4
4
0
0
Registered projects
| Project | District | Registered | Committed date | Status | Band |
|---|---|---|---|---|---|
| Silpa Sr Bamboo Grove | Hyderabad | 3 Mar 2020 | 3 Mar 2022 | STALLED | D |
| Silpa Mahaveer Bougainvillea | Hyderabad | 30 Apr 2021 | 30 Apr 2024 | STALLED | D |
| Silpa Aranya | Hyderabad | 8 Aug 2022 | 8 Aug 2024 | PAST DUE | D |
| Silpa Sindhu Serenity | Hyderabad | 29 Jan 2023 | 29 Jan 2025 | PAST DUE | D |
Track record derived from public TGRERA records as of 2026-07-25. "Past due" = past the completion date committed at registration; Telangana publishes no granted-extension counts.
How many RERA projects does Silpa Infratech Limited have in Telangana?
Silpa Infratech Limited has 4 TGRERA registered projects across Hyderabad. 4 are past their committed completion date.
Does Silpa Infratech Limited have any RERA enforcement in Telangana?
No enforcement action or litigation is flagged on the TGRERA record for their projects.