S L Constructions
S L Constructions has 7 TGRERA registered projects across Medchal-Malkajgiri. 2 are past their committed completion date.
7
2
0
0
Registered projects
| Project | District | Registered | Committed date | Status | Band |
|---|---|---|---|---|---|
| Mukunda Nilayam Block - 2 | Medchal-Malkajgiri | 6 Jun 2022 | 6 Jun 2025 | PAST DUE | B |
| Srinivasam | Medchal-Malkajgiri | 11 Apr 2023 | 11 Apr 2026 | PAST DUE | C |
| Sai Vishnu Nivasam | Medchal-Malkajgiri | 25 Apr 2025 | 24 Apr 2028 | REGISTERED | A |
| Sri Rajarajeshwara Nilayam | Medchal-Malkajgiri | 22 Oct 2024 | 21 Oct 2027 | REGISTERED | A |
| Giri Kunj | Medchal-Malkajgiri | 31 May 2024 | 30 May 2027 | REGISTERED | B |
| Surabhi Homes | Medchal-Malkajgiri | 27 May 2024 | 26 May 2027 | REGISTERED | B |
| Mukunda Nilayam | Medchal-Malkajgiri | 11 May 2021 | 11 May 2027 | REGISTERED | B |
Track record derived from public TGRERA records as of 2026-07-24. "Past due" = past the completion date committed at registration; Telangana publishes no granted-extension counts.
How many RERA projects does S L Constructions have in Telangana?
S L Constructions has 7 TGRERA registered projects across Medchal-Malkajgiri. 2 are past their committed completion date.
Does S L Constructions have any RERA enforcement in Telangana?
No enforcement action or litigation is flagged on the TGRERA record for their projects.