Rami Reddy Constructions
Rami Reddy Constructions has 5 TGRERA registered projects across Ranga Reddy. 5 are past their committed completion date.
5
5
0
0
Registered projects
| Project | District | Registered | Committed date | Status | Band |
|---|---|---|---|---|---|
| Radha Krishna Towers | Ranga Reddy | — | 31 Mar 2020 | PAST DUE | C |
| Ashoo Towers | Ranga Reddy | — | 30 Mar 2020 | PAST DUE | C |
| Bharavi Residency | Ranga Reddy | — | 5 Nov 2024 | PAST DUE | C |
| Royal Castle | Ranga Reddy | 23 Dec 2021 | 23 Dec 2024 | PAST DUE | C |
| Laxmi Ram Haran | Ranga Reddy | 20 Nov 2020 | 18 Dec 2025 | PAST DUE | B |
Track record derived from public TGRERA records as of 2026-07-25. "Past due" = past the completion date committed at registration; Telangana publishes no granted-extension counts.
How many RERA projects does Rami Reddy Constructions have in Telangana?
Rami Reddy Constructions has 5 TGRERA registered projects across Ranga Reddy. 5 are past their committed completion date.
Does Rami Reddy Constructions have any RERA enforcement in Telangana?
No enforcement action or litigation is flagged on the TGRERA record for their projects.