Prime Infratech
Prime Infratech has 3 TGRERA registered projects across Ranga Reddy. 2 are past their committed completion date.
3
2
0
0
Registered projects
| Project | District | Registered | Committed date | Status | Band |
|---|---|---|---|---|---|
| Prime Alpenia | Ranga Reddy | — | 16 Oct 2021 | STALLED | D |
| Prime Solitaire | Ranga Reddy | — | 4 Sep 2022 | STALLED | D |
| Prime Titania | Ranga Reddy | 5 Feb 2021 | 4 Feb 2027 | REGISTERED | A |
Track record derived from public TGRERA records as of 2026-07-24. "Past due" = past the completion date committed at registration; Telangana publishes no granted-extension counts.
How many RERA projects does Prime Infratech have in Telangana?
Prime Infratech has 3 TGRERA registered projects across Ranga Reddy. 2 are past their committed completion date.
Does Prime Infratech have any RERA enforcement in Telangana?
No enforcement action or litigation is flagged on the TGRERA record for their projects.