Jubilee Constructions has 8 TGRERA registered projects across Warangal Urban. 5 are past their committed completion date.
8
5
0
0
Registered projects
| Project | District | Registered | Committed date | Status | Band |
|---|---|---|---|---|---|
| Jubilee Aashirwad | Warangal Urban | 4 May 2018 | 4 May 2024 | STALLED | C |
| Jubilee Mangalam A | Warangal Urban | 27 Dec 2021 | 27 Dec 2024 | PAST DUE | C |
| Jubilee Mangalama B | Warangal Urban | 27 Dec 2021 | 27 Dec 2024 | PAST DUE | C |
| Jubilee Srinivasam | Warangal Urban | 26 Nov 2019 | 26 Nov 2025 | PAST DUE | B |
| Jubilee Hemalatha Residency | Warangal Urban | 20 Jul 2024 | 20 Jul 2027 | REGISTERED | B |
| Jubilee Shubha Tulasi | Warangal Urban | 8 May 2024 | 8 May 2027 | REGISTERED | B |
| Ratnakara Residency | Warangal Urban | 9 Nov 2023 | 9 Nov 2026 | REGISTERED | B |
| Jubilee Emerald | Warangal Urban | 7 Jul 2023 | 7 Jul 2026 | PAST DUE | C |
Track record derived from public TGRERA records as of 2026-07-24. "Past due" = past the completion date committed at registration; Telangana publishes no granted-extension counts.
How many RERA projects does Jubilee Constructions have in Telangana?
Jubilee Constructions has 8 TGRERA registered projects across Warangal Urban. 5 are past their committed completion date.
Does Jubilee Constructions have any RERA enforcement in Telangana?
No enforcement action or litigation is flagged on the TGRERA record for their projects.