Hirav Infra
Hirav Infra has 2 TGRERA registered projects across Ranga Reddy. 1 are past their committed completion date.
2
1
0
0
Registered projects
| Project | District | Registered | Committed date | Status | Band |
|---|---|---|---|---|---|
| Yogine Sierra | Ranga Reddy | 27 Jan 2018 | 27 Jan 2024 | STALLED | D |
| Yogine Sierra | Ranga Reddy | 5 Nov 2024 | 5 Nov 2027 | REGISTERED | A |
Track record derived from public TGRERA records as of 2026-07-24. "Past due" = past the completion date committed at registration; Telangana publishes no granted-extension counts.
How many RERA projects does Hirav Infra have in Telangana?
Hirav Infra has 2 TGRERA registered projects across Ranga Reddy. 1 are past their committed completion date.
Does Hirav Infra have any RERA enforcement in Telangana?
No enforcement action or litigation is flagged on the TGRERA record for their projects.
Shortlisting here? Verify before you pay.
We check title and RERA standing, benchmark the price against registration data, and negotiate with the builder on your side. Free first consultation.