Gokul Constructions
Gokul Constructions has 13 TGRERA registered projects across Hyderabad, Ranga Reddy. 9 are past their committed completion date.
13
9
0
0
Registered projects
| Project | District | Registered | Committed date | Status | Band |
|---|---|---|---|---|---|
| Gokul S Nandanam Block C | Hyderabad | 2 Mar 2018 | 31 Dec 2019 | PAST DUE | D |
| Gokul S Nandanam Block B | Hyderabad | 8 Jan 2018 | 31 Dec 2019 | PAST DUE | D |
| Gokul S Nandanam Block A | Hyderabad | 1 Dec 2017 | 31 Dec 2019 | PAST DUE | D |
| Gokul Grand | Hyderabad | 21 Apr 2018 | 21 Apr 2024 | PAST DUE | D |
| Gokuls Bhuvanam | Hyderabad | 27 Jan 2020 | 30 Jun 2025 | PAST DUE | B |
| Gokul Pride | Hyderabad | 16 Oct 2019 | 16 Oct 2025 | PAST DUE | B |
| Gokul Elite | Ranga Reddy | 1 May 2023 | 1 May 2026 | PAST DUE | C |
| Gokul Prime | Ranga Reddy | 1 May 2023 | 1 May 2026 | PAST DUE | C |
| Gokul Garnet | Ranga Reddy | 24 Jul 2023 | 24 Jul 2026 | DUE SOON | B |
| Gokul Shine | Ranga Reddy | 15 Jul 2023 | 15 Jul 2026 | PAST DUE | C |
| Gokul Saianurag Residency | Ranga Reddy | 9 Jul 2021 | 9 Jul 2027 | REGISTERED | A |
| Gokul Plaza | Ranga Reddy | 10 Jun 2021 | 10 Jun 2027 | REGISTERED | A |
| Gokul Heights | Ranga Reddy | 22 May 2021 | 27 May 2027 | REGISTERED | A |
Track record derived from public TGRERA records as of 2026-07-24. "Past due" = past the completion date committed at registration; Telangana publishes no granted-extension counts.
How many RERA projects does Gokul Constructions have in Telangana?
Gokul Constructions has 13 TGRERA registered projects across Hyderabad, Ranga Reddy. 9 are past their committed completion date.
Does Gokul Constructions have any RERA enforcement in Telangana?
No enforcement action or litigation is flagged on the TGRERA record for their projects.
Shortlisting here? Verify before you pay.
We check title and RERA standing, benchmark the price against registration data, and negotiate with the builder on your side. Free first consultation.