Elements

Elements has 4 TGRERA registered projects across Hyderabad. 3 are past their committed completion date.

4
3
0
0

Registered projects

ProjectDistrictRegisteredCommitted dateStatusBand
Rock Town Hyderabad 28 Mar 2019 28 Mar 2025 PAST DUE C
White Riviera Hyderabad 9 Jul 2019 9 Jul 2025 PAST DUE B
X-Brique Hyderabad 27 Sep 2019 27 Sep 2025 PAST DUE C
Marvella Hyderabad 26 Oct 2022 26 Oct 2027 REGISTERED B

Track record derived from public TGRERA records as of 2026-07-25. "Past due" = past the completion date committed at registration; Telangana publishes no granted-extension counts.

How many RERA projects does Elements have in Telangana?

Elements has 4 TGRERA registered projects across Hyderabad. 3 are past their committed completion date.

Does Elements have any RERA enforcement in Telangana?

No enforcement action or litigation is flagged on the TGRERA record for their projects.