Arrow Infratech has 2 TGRERA registered projects across Ranga Reddy. 2 are past their committed completion date.

2
2
0
0

Registered projects

ProjectDistrictRegisteredCommitted dateStatusBand
Bhonagiri Residency Ranga Reddy 23 Feb 2022 23 Feb 2025 PAST DUE C
Kundan Ranga Reddy 12 Feb 2020 12 Feb 2026 PAST DUE B

Track record derived from public TGRERA records as of 2026-07-26. "Past due" = past the completion date committed at registration; Telangana publishes no granted-extension counts.

How many RERA projects does Arrow Infratech have in Telangana?

Arrow Infratech has 2 TGRERA registered projects across Ranga Reddy. 2 are past their committed completion date.

Does Arrow Infratech have any RERA enforcement in Telangana?

No enforcement action or litigation is flagged on the TGRERA record for their projects.