Ananda Homes
Ananda Homes has 7 TGRERA registered projects across Ranga Reddy. 5 are past their committed completion date.
7
5
0
0
Registered projects
| Project | District | Registered | Committed date | Status | Band |
|---|---|---|---|---|---|
| Eucalyptus | Ranga Reddy | 9 May 2019 | 31 Aug 2023 | STALLED | C |
| Palm Springs | Ranga Reddy | 27 Sep 2018 | 31 Aug 2023 | PAST DUE | D |
| Urbans Dale | Ranga Reddy | 21 Aug 2019 | 21 Aug 2024 | PAST DUE | D |
| Tuberose | Ranga Reddy | 4 Feb 2021 | 4 Feb 2025 | PAST DUE | C |
| Rose Bay | Ranga Reddy | 24 Aug 2020 | 24 Aug 2025 | PAST DUE | B |
| The Legacey By Ananda Homes | Ranga Reddy | 25 Jun 2024 | 25 Jun 2029 | REGISTERED | B |
| The Drizzle | Ranga Reddy | 15 Jul 2022 | 15 Jul 2028 | REGISTERED | A |
Track record derived from public TGRERA records as of 2026-07-24. "Past due" = past the completion date committed at registration; Telangana publishes no granted-extension counts.
How many RERA projects does Ananda Homes have in Telangana?
Ananda Homes has 7 TGRERA registered projects across Ranga Reddy. 5 are past their committed completion date.
Does Ananda Homes have any RERA enforcement in Telangana?
No enforcement action or litigation is flagged on the TGRERA record for their projects.