TN/29/Building/419/2022PAST COMMITTED DATE

ICIPL Swarn is registered with TNRERA as TN/29/Building/419/2022 (Building registration, 2022). The promoter is M/s. Intouch Construction and Infrastructure Private Limited, Rep. by its Managing Director, Thiru. P.Vijaikumar. The RERA-committed completion date is 31 Mar 2024 — that date has now passed. Committed dates are legally binding under RERA.

13 Oct 2022
31 Mar 2024
0

Latest quarterly progress filing — December 2023

Caution: the RERA-committed completion date has passed, and the last quarterly filing reported 85% physical completion. Ask the builder for the current status and updated timeline before paying anything.

85%
85%

Stage, as filed: Block/Tower, Floor wise completed.

Source: the project's Quarterly Progress Report filed with TNRERA (as on the quarter shown; may not reflect current status).

About this registration

Project Name: “ICIPL Swarn” - Construction of Registration of Stilt Floor + 3rd Floor (Part) Residential Building at Plot Nos.23 and 24, Vijaya Lakshmi Nagar, Korattur Village, Chennai comprised in S.Nos.760/4, 760/5B, 760/6, T.S.Nos.10/33, 10/35, 10/36, 10/4, 10/32, 10/34 (as per Document), S.Nos.760/2, 760/3B, 760/3B part, 4B, 4B part, 5A, 5A part, 5B, 2, 6, 763/2 part, T.S.Nos.10/4, 10/32, 10/33, 10/34, 10/35, 10/36 (as per Patta), Block No.9, Ward-E of Korattur Village, Ambattur Taluk within the limit of Greater Chennai Corporation.

Approval: CMDA issued Planning Permission No. PP/NHRB/145/2022/A & B in Letter No. PP/NHRB/N/027/2022, dated 26.05.2022. The Executive Engineer (T.P), Greater Chennai Corporation issued Building Permission No. CEBA/WDCN07/00184/20

Status on register: Progress of Work as on December 2023

Builder track record: M/s. Intouch Construction and Infrastructure Private Limited

M/s. Intouch Construction and Infrastructure Private Limited, Rep. by its Managing Director, Thiru. P.Vijaikumar has 1 project on the TNRERA register since 2022, with no completion-date extensions on record.

Frequently asked

Is ICIPL Swarn RERA registered?

Yes — registered with TNRERA as TN/29/Building/419/2022 in 2022. Always quote this number when dealing with the builder; unregistered projects cannot legally be marketed or sold in Tamil Nadu.

When will ICIPL Swarn be completed?

The RERA-committed completion date is 31 Mar 2024. No deadline extensions are on record.

Who is the builder of ICIPL Swarn?

M/s. Intouch Construction and Infrastructure Private Limited, Rep. by its Managing Director, Thiru. P.Vijaikumar.

← All Ambattur–Avadi Belt projects and market data

Source documents on TNRERA

These are the government's own filed documents for this project. We link them directly — verify anything on this page against them.

Shortlisting here? Verify before you pay.

We check title and RERA standing, benchmark the price against registration data, and negotiate with the builder on your side. Free first consultation.