VerifyRERAEvery project's full RERA record. Verified in seconds.
Home/Localities/Ambattur–Avadi Belt/Veera Ala Garden

Veera Ala Garden

TN/29/Building/309/2021PAST COMMITTED DATE

Veera Ala Garden is registered with TNRERA as TN/29/Building/309/2021 (Building registration, 2021). The promoter is 1) Thiru. R.J.Veeraraghavan, Vira Sanctum. The RERA-committed completion date is 31 Dec 2022 — that date has now passed. Committed dates are legally binding under RERA.

21 Sep 2021
31 Dec 2022
9
0

Latest quarterly progress filing — March 2023

Caution: the RERA-committed completion date has passed, and the last quarterly filing reported 95% physical completion. Ask the builder for the current status and updated timeline before paying anything.

95%
95%

Stage, as filed: Block/Tower, Floor wise

Source: the project's Quarterly Progress Report filed with TNRERA (as on the quarter shown; may not reflect current status).

About this registration

Project Name: “Veera Ala Garden” - Construction of Stilt Floor + 3 Floors with 9 dwelling units at Plot No.2B, U.R. Nagar Extension, Padi, Chennai - 600050 comprised in S.Nos.11/1, 11/2, 11/1A1, 11/1A2, 11/2B1 & 11/2B2 (as per Doc.), S.Nos.11/1A1 part, 11/2B1 part, 11/20 part, Ward No.I, T.S.No.15, Block No.14 of Padi Village, Ambattur Taluk, Chennai District.

Approval: Planning Permission issued by the Chief Planner / Area Plans Unit / CMDA / Chennai vide Letter No. PP/NHRB/N/0538/2020, dated 23.12.2020. Building Permission issued by the Executive Engineer (T.P.) / Greater Chennai Corp

Status on register: Progress of Work as on March 2023

Builder track record: 1) Thiru. R.J.Veeraraghavan, Vira Sanctum

1) Thiru. R.J.Veeraraghavan, Vira Sanctum has 1 project on the TNRERA register since 2021, with no completion-date extensions on record.

Frequently asked

Is Veera Ala Garden RERA registered?

Yes — registered with TNRERA as TN/29/Building/309/2021 in 2021. Always quote this number when dealing with the builder; unregistered projects cannot legally be marketed or sold in Tamil Nadu.

When will Veera Ala Garden be completed?

The RERA-committed completion date is 31 Dec 2022. No deadline extensions are on record.

Who is the builder of Veera Ala Garden?

1) Thiru. R.J.Veeraraghavan, Vira Sanctum.

← All Ambattur–Avadi Belt projects and market data

Source documents on TNRERA

These are the government's own filed documents for this project. We link them directly — verify anything on this page against them.

Shortlisting here? Verify before you pay.

We check title and RERA standing, benchmark the price against registration data, and negotiate with the builder on your side. Free first consultation.