VerifyRERAEvery project's full RERA record. Verified in seconds.
Home/Localities/OMR Corridor/Ridgewood Condos

Ridgewood Condos

TN/29/Building/0425/2020PAST COMMITTED DATE

Ridgewood Condos is registered with TNRERA as TN/29/Building/0425/2020 (Building registration, 2020). The promoter is M/s. Shri Raman Developers, who has 3 projects on the TNRERA register. The RERA-committed completion date is 31 Dec 2021 — that date has now passed. Committed dates are legally binding under RERA.

19 Nov 2020
31 Dec 2021
9
0

Latest quarterly progress filing

Caution: the RERA-committed completion date has passed, and the last quarterly filing reported 30% physical completion. Ask the builder for the current status and updated timeline before paying anything.

30%

Stage, as filed: Block/Tower, Floor wise Block – B

Source: the project's Quarterly Progress Report filed with TNRERA (as on the quarter shown; may not reflect current status).

About this registration

Project Name: “Ridgewood Condos” - Construction of Plot No.A - Stilt Floor + 3 Floors residential building with 9 dwelling units and Plot No.B - Stilt Floor + 3 Floors residential building with 9 dwelling units at Kannadasan Nagar, Pallikaranai, Chennai comprised in S.No.695/5A & 695/5B as per Patta, New S.No.695/5A1B, 695/43 of Pallikaranai Village, Sholinganallur Taluk, Chennai.

Approval: Plot No.A - Planning Permission No. PPA/WDCN/1407292/2019 & Building Permission No. BA/WDCN/14/00013/2020 dated 13.01.2020 issued by Greater Chennai Corporation. Plot No.B - Planning Permission No.PPA/WDCN/14/07293/2019

Status on register: Progress of Work as on December 2020

Builder track record: M/s. Shri Raman Developers

M/s. Shri Raman Developers has 3 projects on the TNRERA register since 2020, with no completion-date extensions on record. See the full record →

Frequently asked

Is Ridgewood Condos RERA registered?

Yes — registered with TNRERA as TN/29/Building/0425/2020 in 2020. Always quote this number when dealing with the builder; unregistered projects cannot legally be marketed or sold in Tamil Nadu.

When will Ridgewood Condos be completed?

The RERA-committed completion date is 31 Dec 2021. No deadline extensions are on record.

Who is the builder of Ridgewood Condos?

M/s. Shri Raman Developers, with 3 projects on the TNRERA register and no completion-date extensions on record.

← All OMR Corridor projects and market data

Source documents on TNRERA

These are the government's own filed documents for this project. We link them directly — verify anything on this page against them.

Shortlisting here? Verify before you pay.

We check title and RERA standing, benchmark the price against registration data, and negotiate with the builder on your side. Free first consultation.