Skyline Citadal
Skyline Citadal is registered with TNRERA as TN/29/Building/0354/2021 (Building registration, 2021). The promoter is Thiru. Mohammed Qadeer Ahmed, Proprietor, M/s. Skyline Construction. The RERA-committed completion date is 30 Jun 2024 — that date has now passed. Committed dates are legally binding under RERA.
About this registration
Project Name: “Skyline Citadal” - Construction of Stilt Floor + 5 Floors with 15 dwelling units at New Door No.33 & 35, Old Door No.15 & 16, Deivasigamani Road, Royapettah, Chennai comprised in R.S.No.1149/14 & 1149/41, Block No.24 of Mylapore Village & Taluk, Chennai District.
Approval: Planning Permission issued by the Chief Planner / B-South / Area Plans Unit / CMDA / Chennai vide Letter No. PP/NHRB/S(B1)/0310/2020, dated 15/4/2021. Building Permission issued by the Executive Engineer (T.P.) / Greater
Builder track record: Thiru. Mohammed Qadeer Ahmed, Proprietor, M/s. Skyline Const
Thiru. Mohammed Qadeer Ahmed, Proprietor, M/s. Skyline Construction has 1 project on the TNRERA register since 2021, with no completion-date extensions on record.
Frequently asked
Is Skyline Citadal RERA registered?
Yes — registered with TNRERA as TN/29/Building/0354/2021 in 2021. Always quote this number when dealing with the builder; unregistered projects cannot legally be marketed or sold in Tamil Nadu.
When will Skyline Citadal be completed?
The RERA-committed completion date is 30 Jun 2024. No deadline extensions are on record.
Who is the builder of Skyline Citadal?
Thiru. Mohammed Qadeer Ahmed, Proprietor, M/s. Skyline Construction.
← All Central Chennai projects and market data
Source documents on TNRERA
These are the government's own filed documents for this project. We link them directly — verify anything on this page against them.
Shortlisting here? Verify before you pay.
We check title and RERA standing, benchmark the price against registration data, and negotiate with the builder on your side. Free first consultation.