Home/Localities/Central Chennai/Construction of Registration of Stilt Floor + 5 Floors

Construction of Registration of Stilt Floor + 5 Floors

TN/29/Building/0330/2023PAST COMMITTED DATE

Construction of Registration of Stilt Floor + 5 Floors is registered with TNRERA as TN/29/Building/0330/2023 (Building registration, 2023). The promoter is M/s. Swathi Builders, Rep. by Managing Partner, Thiru. K.S.Prabhakar. The RERA-committed completion date is 30 May 2025 — that date has now passed. Committed dates are legally binding under RERA.

1 Aug 2023
30 May 2025
15
0

Latest quarterly progress filing

Caution: the RERA-committed completion date has passed, and the last quarterly filing reported 50% physical completion. Ask the builder for the current status and updated timeline before paying anything.

50%
50%

Stage, as filed: Block/Tower, Floor wise Stilt and ground and first floor roof completed.

Source: the project's Quarterly Progress Report filed with TNRERA (as on the quarter shown; may not reflect current status).

About this registration

Construction of Registration of Stilt Floor + 5 Floors Residential Building with 15 dwelling units at Old Door No.89, New Door No.184, Habibullah Road, T.Nagar Village, Chennai comprised in Old S.No.96/1, T.S.No.6781, Block No.106 of T.Nagar Village, Guindy Taluk, Chennai District.

Approval: The CMDA issued the Planning Permission No. OL-PP/NHRB/0102/2023 in Letter No. CMDA/PP/NHRB/C/0026/2023, dated 15.03.2023. The Greater Chennai Corporation issued the Building Permission in Letter RC.No. CEBA/WDCN09/00138

Status on register: Progress of Work as on June 2024

Builder track record: M/s. Swathi Builders, Rep. by Managing Partner, Thiru. K.S.P

M/s. Swathi Builders, Rep. by Managing Partner, Thiru. K.S.Prabhakar has 1 project on the TNRERA register since 2023, with no completion-date extensions on record.

Frequently asked

Is Construction of Registration of Stilt Floor + 5 Floors RERA registered?

Yes — registered with TNRERA as TN/29/Building/0330/2023 in 2023. Always quote this number when dealing with the builder; unregistered projects cannot legally be marketed or sold in Tamil Nadu.

When will Construction of Registration of Stilt Floor + 5 Floors be completed?

The RERA-committed completion date is 30 May 2025. No deadline extensions are on record.

Who is the builder of Construction of Registration of Stilt Floor + 5 Floors?

M/s. Swathi Builders, Rep. by Managing Partner, Thiru. K.S.Prabhakar.

← All Central Chennai projects and market data

Source documents on TNRERA

These are the government's own filed documents for this project. We link them directly — verify anything on this page against them.

Shortlisting here? Verify before you pay.

We check title and RERA standing, benchmark the price against registration data, and negotiate with the builder on your side. Free first consultation.