TN/29/Building/0319/2022PAST COMMITTED DATE

Pushkar is registered with TNRERA as TN/29/Building/0319/2022 (Building registration, 2022). The promoter is 1) M/s. Pushkar Properties Pvt. Ltd. (Promoter) and Tvl. 2) O.A.Radhakrishnan. The RERA-committed completion date is 30 Jan 2024 — that date has now passed. Committed dates are legally binding under RERA.

24 Aug 2022
30 Jan 2024
8
0

Latest quarterly progress filing — December 2023

100%

Stage, as filed: Block/Tower, Floor wise Flats are handed over.

Source: the project's Quarterly Progress Report filed with TNRERA (as on the quarter shown; may not reflect current status).

Apartment sizes (carpet area)

RERA carpet areas for this project, read from the filed area statement — the real usable floor area, excluding balcony and common space.

ConfigurationCarpet area (sq.ft)Units
3BHK1,0831

100% of units have a balcony on the filed area statement, typically around 48 sq.ft.

Machine-read from the filed carpet-area statement (low OCR confidence — verify against source). Normalised to sq.ft from sq.m. View the original document filed with TNRERA ↗

About this registration

Project Name: “Pushkar’s Nalanda Enclave” - Construction of Registration of Stilt + 4 Floors residential building with 8 dwelling units at TNHB Block No.187, Old Door No.187, New Door No.352, Shanthi Colony, 4th Avenue, Anna Nagar, Chennai comprised in Old S.No.227/4 part, T.S.No.126/1, Block No.21 of Koyembedu Village, Chennai.

Approval: CMDA issued Planning Permission No. PP/NHRB/126/2022 in Letter No. PP/NHRB/C/0627/2021, dated 29.04.2022. Greater Chennai Corporation issued Building Permission No. CEBA/WDCN08/00190/2022, dated 28.06.2022

Status on register: Progress of Work as on December 2023

Builder track record: 1) M/s. Pushkar Properties Pvt. Ltd. (Promoter) and Tvl. 2)

1) M/s. Pushkar Properties Pvt. Ltd. (Promoter) and Tvl. 2) O.A.Radhakrishnan has 1 project on the TNRERA register since 2022, with no completion-date extensions on record.

Frequently asked

Is Pushkar RERA registered?

Yes — registered with TNRERA as TN/29/Building/0319/2022 in 2022. Always quote this number when dealing with the builder; unregistered projects cannot legally be marketed or sold in Tamil Nadu.

When will Pushkar be completed?

The RERA-committed completion date is 30 Jan 2024. No deadline extensions are on record.

Who is the builder of Pushkar?

1) M/s. Pushkar Properties Pvt. Ltd. (Promoter) and Tvl. 2) O.A.Radhakrishnan.

← All Ambattur–Avadi Belt projects and market data

Source documents on TNRERA

These are the government's own filed documents for this project. We link them directly — verify anything on this page against them.

Shortlisting here? Verify before you pay.

We check title and RERA standing, benchmark the price against registration data, and negotiate with the builder on your side. Free first consultation.