Nahar Tulasi
Nahar Tulasi is registered with TNRERA as TN/29/Building/0318/2020 (Building registration, 2020). The promoter is M/s. Nahar Foundations’s Private Limited, X4, Nahar Villa, who has 2 projects on the TNRERA register. The RERA-committed completion date is 31 Jul 2023 — that date has now passed. Committed dates are legally binding under RERA.
Latest quarterly progress filing — May 2022
Stage, as filed: Block/Tower, Floor wise manner.
Source: the project's Quarterly Progress Report filed with TNRERA (as on the quarter shown; may not reflect current status).
About this registration
Project Name: “Nahar Tulasi” - Construction of Stilt Floor + 4 Floors in which Promoter Share of Flats – 1st Floor: Flat – B, C, 2nd Floor: Flat – B, 3rd Floor: Flat – A, 4th Floor: Flat – A & B at Block No.H-15, Door No.13, South Avenue, 25th East Street, Kamaraj Nagar in Comprised in Old S.No.70 Part, T.S.No.11, Block No.29 of Thiruvanmiyur Village, Velachery Taluk, Chennai District.
Approval: Planning Permission issued by the Chief Planner, Area Plans Unit, CMDA, Chennai, vide Letter No. PP/NHRB/S(B1)/1181/2019, dated 03.02.2020. Building Permission issued by the Executive Engineer (T.P.), Greater Chennai Cor
Status on register: Completed
Builder track record: M/s. Nahar Foundations’s Private Limited, X4, Nahar Villa
M/s. Nahar Foundations’s Private Limited, X4, Nahar Villa has 2 projects on the TNRERA register since 2020, with no completion-date extensions on record. See the full record →
Frequently asked
Is Nahar Tulasi RERA registered?
Yes — registered with TNRERA as TN/29/Building/0318/2020 in 2020. Always quote this number when dealing with the builder; unregistered projects cannot legally be marketed or sold in Tamil Nadu.
When will Nahar Tulasi be completed?
The RERA-committed completion date is 31 Jul 2023. No deadline extensions are on record.
Who is the builder of Nahar Tulasi?
M/s. Nahar Foundations’s Private Limited, X4, Nahar Villa, with 2 projects on the TNRERA register and no completion-date extensions on record.
← All Central Chennai projects and market data
Source documents on TNRERA
These are the government's own filed documents for this project. We link them directly — verify anything on this page against them.
Shortlisting here? Verify before you pay.
We check title and RERA standing, benchmark the price against registration data, and negotiate with the builder on your side. Free first consultation.