Home/Localities/Ambattur–Avadi Belt/Construction of Stilt floor + 4 Floors

Construction of Stilt floor + 4 Floors

TN/29/Building/0193/2019PAST COMMITTED DATE

Construction of Stilt floor + 4 Floors is registered with TNRERA as TN/29/Building/0193/2019 (Building registration, 2019). The promoter is Tmt. Akshaya, Proprietor, M/s. JK Foundation & 20 Owners. The RERA-committed completion date is 1 Dec 2022 — that date has now passed. Committed dates are legally binding under RERA.

9 Nov 2019
1 Dec 2022
28
0

Latest quarterly progress filing

Caution: the RERA-committed completion date has passed, and the last quarterly filing reported 2% physical completion. Ask the builder for the current status and updated timeline before paying anything.

2%

Stage, as filed: Block/Tower, Floor wise work completed 26 piles pending

Source: the project's Quarterly Progress Report filed with TNRERA (as on the quarter shown; may not reflect current status).

Apartment sizes (carpet area)

RERA carpet areas for this project, read from the filed area statement — the real usable floor area, excluding balcony and common space.

Carpet areas range from 369 to 499 sq.ft (median 477 sq.ft) across 3 units.

67% of units have a balcony on the filed area statement, typically around 146 sq.ft.

Machine-read from the filed carpet-area statement. Normalised to sq.ft from sq.m. View the original document filed with TNRERA ↗

About this registration

Construction of Stilt floor + 4 Floors Residential Building with 28 dwelling units at TNHB Block Nos.SH-47, SH-48, SH-49, 25th Street, Korattur Village, Chennai-80, comprised in Old S.No.1302/1A Pt, 2B pt, 1323/1A1 pt, T.S No.17-47/6, Ward E, Block No.46 of Korattur Village, Chennai.

Approval: Planning Permission No. B/Spl.Bldg/187/2016 dated 30.08.2016 issued by CMDA in Letter No. B3/8365/2015 dated 30.8.2016 and the Building Permission No:CEBA/WDCN07/00128/2019 dated 25.06.2019 issued by the Greater Chennai

Status on register: Progress of Work as on March 2022

Builder track record: Tmt. Akshaya, Proprietor, M/s. JK Foundation & 20 Owners

Tmt. Akshaya, Proprietor, M/s. JK Foundation & 20 Owners has 1 project on the TNRERA register since 2019, with no completion-date extensions on record.

Frequently asked

Is Construction of Stilt floor + 4 Floors RERA registered?

Yes — registered with TNRERA as TN/29/Building/0193/2019 in 2019. Always quote this number when dealing with the builder; unregistered projects cannot legally be marketed or sold in Tamil Nadu.

When will Construction of Stilt floor + 4 Floors be completed?

The RERA-committed completion date is 1 Dec 2022. No deadline extensions are on record.

Who is the builder of Construction of Stilt floor + 4 Floors?

Tmt. Akshaya, Proprietor, M/s. JK Foundation & 20 Owners.

← All Ambattur–Avadi Belt projects and market data

Source documents on TNRERA

These are the government's own filed documents for this project. We link them directly — verify anything on this page against them.

Shortlisting here? Verify before you pay.

We check title and RERA standing, benchmark the price against registration data, and negotiate with the builder on your side. Free first consultation.