TN/29/Building/0185/2019PAST COMMITTED DATE

Utsav is registered with TNRERA as TN/29/Building/0185/2019 (Building registration, 2019). The promoter is M/s. SANKLECHA INFRA PROJECTS PRIVATE LIMITED, who has 2 projects on the TNRERA register. The RERA-committed completion date is 30 Sep 2021 — that date has now passed. Committed dates are legally binding under RERA.

6 Nov 2019
30 Sep 2021
112
0

A quarterly progress filing exists for this project on the TNRERA register as a scanned document; we haven't machine-read it yet.

About this registration

Project Name: "Utsav" - Construction of Wing T2 of Stilt Floor + 16 Floors Residential Building with 112 dwelling units at Door Nos.20/21, 25, 274, 290/1 & 292, Cooks Road, Somasundaram Nagar, Krishnadas Road, Somasundaram Nagar Main Road & Somasundaram Nagar 1st Street, Otteri, Chennai-12 comprised in R.S.No.273/48 part and 274/49 part, Block No.17 of Perambur Village, Chennai.

Approval: Approved by CMDA Planning Permission No.C/PP/MSB/36(S-01 to S-43)/2018 in Letter No.C3(N)/941/2017 dated 20.09.2018 and the Building Permission No.CEBA/WDCN06/00283/2018, dated 01.10.2018 issued by the Greater Chennai Co

Status on register: Progress of Work as on June 2024

Builder track record: M/s. SANKLECHA INFRA PROJECTS PRIVATE LIMITED

M/s. SANKLECHA INFRA PROJECTS PRIVATE LIMITED has 2 projects on the TNRERA register since 2018, with no completion-date extensions on record. See the full record →

Frequently asked

Is Utsav RERA registered?

Yes — registered with TNRERA as TN/29/Building/0185/2019 in 2019. Always quote this number when dealing with the builder; unregistered projects cannot legally be marketed or sold in Tamil Nadu.

When will Utsav be completed?

The RERA-committed completion date is 30 Sep 2021. No deadline extensions are on record.

Who is the builder of Utsav?

M/s. SANKLECHA INFRA PROJECTS PRIVATE LIMITED, with 2 projects on the TNRERA register and no completion-date extensions on record.

← All North Chennai projects and market data

Source documents on TNRERA

These are the government's own filed documents for this project. We link them directly — verify anything on this page against them.

Shortlisting here? Verify before you pay.

We check title and RERA standing, benchmark the price against registration data, and negotiate with the builder on your side. Free first consultation.