Casagrand Cloud-9

TN/29/Building/0184/2023REGISTERED

Casagrand Cloud-9 is registered with TNRERA as TN/29/Building/0184/2023 (Building registration, 2023). The promoter is M/s. Casa Grande Milestone Private Limited, who has 2 projects on the TNRERA register. The RERA-committed completion date is 10 Oct 2026 (about 3 months away). Committed dates are legally binding under RERA.

28 Apr 2023
10 Oct 2026
331
0

Latest quarterly progress filing — December 2025

65%

Stage, as filed: Block/Tower, Floor-wise completed and finishing work in progress – 65%

Source: the project's Quarterly Progress Report filed with TNRERA (as on the quarter shown; may not reflect current status).

About this registration

Project Name: “Casagrand Cloud-9” - Construction of Registration of High Rise Building (HRB) Group Development 2 Blocks for Residential Building consisting of Extended Combined Basement Floor for Block-1 & 2, Block-1: Partly Stilt Floor / Party Ground Floor + 19 Floors with 331 dwelling units, Block-2 (Amenity Block): Ground Floor + 4 Floors (NHRB) incidental activities with Yoga, Association Room, Indoor Games Room, Home Theatre, Gym, Meditation Room, Creche, Shower Room, Dress Change Room and Open Swimming Pool at TNHB Main Road, Sholinganallur, Chennai comprised in Survey Nos.307/2B & 310/2B of Sholinganallur Village, Sholinganallur Taluk, Chennai District.

Approval: The CMDA issued Planning Permission No. OL-PP/HRB/0002/2023 in Letter No. CMDA/PP/HRB/S/0449/2022, dated 17.04.2023. The Greater Chennai Corporation issued Building Permission in Letter RC.No. CEBA/WDCN15/00169/2023, dat

Status on register: Progress of Work as on December 2025

Builder track record: M/s. Casa Grande Milestone Private Limited

M/s. Casa Grande Milestone Private Limited has 2 projects on the TNRERA register since 2021, with no completion-date extensions on record. See the full record →

Frequently asked

Is Casagrand Cloud-9 RERA registered?

Yes — registered with TNRERA as TN/29/Building/0184/2023 in 2023. Always quote this number when dealing with the builder; unregistered projects cannot legally be marketed or sold in Tamil Nadu.

When will Casagrand Cloud-9 be completed?

The RERA-committed completion date is 10 Oct 2026. No deadline extensions are on record.

Who is the builder of Casagrand Cloud-9?

M/s. Casa Grande Milestone Private Limited, with 2 projects on the TNRERA register and no completion-date extensions on record.

← All OMR Corridor projects and market data

Source documents on TNRERA

These are the government's own filed documents for this project. We link them directly — verify anything on this page against them.

Shortlisting here? Verify before you pay.

We check title and RERA standing, benchmark the price against registration data, and negotiate with the builder on your side. Free first consultation.