Malhotra Gardenia
Malhotra Gardenia is registered with TNRERA as TN/29/Building/0142/2022 (Building registration, 2022). The promoter is Thiru. K.Ramesh (Proprietor), M/s. Kay Arr & Co.. The RERA-committed completion date is 28 Nov 2026 (about 5 months away). Committed dates are legally binding under RERA.
Latest quarterly progress filing — SEPTEMBER 2024
Stage, as filed: Block/Tower, Floor wise completed, Lift work in progress. EB, CMWSSB completed.
Source: the project's Quarterly Progress Report filed with TNRERA (as on the quarter shown; may not reflect current status).
Apartment sizes (carpet area)
RERA carpet areas for this project, read from the filed area statement — the real usable floor area, excluding balcony and common space.
| Configuration | Carpet area (sq.ft) | Units |
|---|---|---|
| 3BHK | 1,208–1,491 | 6 |
| 2BHK | 644–1,314 | 3 |
Machine-read from the filed carpet-area statement. Normalised to sq.ft from sq.m. View the original document filed with TNRERA ↗
About this registration
Project Name: “Malhotra Gardenia” - Construction of Registration of Promoter share of Flat Nos.201, 202 in 2nd Floor and 301 in 3rd Floor (3 Flats) in Stilt + 4 Floors residential building with 9 dwelling units at Old Door No.37/1, New Door No.39, Plot No.71 of Gill Nagar, 2nd Street, Choolaimedu, Chennai - 600094 comprised in T.S.No.44/111, Block No.13 of Puliyur Village, Egmore Taluk, Chennai.
Approval: CMDA issued Planning Permission No. PP/NHRB/338/2021 in Letter No. PP/NHRB/C/520/2021, dated 29.11.2021. Greater Chennai Corporation issued Building Permission No. CEBA/WDCN09/00016/2022, dated 27.01.2022
Status on register: Progress of Work as on September 2024
Builder track record: Thiru. K.Ramesh (Proprietor), M/s. Kay Arr & Co.
Thiru. K.Ramesh (Proprietor), M/s. Kay Arr & Co. has 1 project on the TNRERA register since 2022, with no completion-date extensions on record.
Frequently asked
Is Malhotra Gardenia RERA registered?
Yes — registered with TNRERA as TN/29/Building/0142/2022 in 2022. Always quote this number when dealing with the builder; unregistered projects cannot legally be marketed or sold in Tamil Nadu.
When will Malhotra Gardenia be completed?
The RERA-committed completion date is 28 Nov 2026. No deadline extensions are on record.
Who is the builder of Malhotra Gardenia?
Thiru. K.Ramesh (Proprietor), M/s. Kay Arr & Co..
← All Central Chennai projects and market data
Source documents on TNRERA
These are the government's own filed documents for this project. We link them directly — verify anything on this page against them.
Shortlisting here? Verify before you pay.
We check title and RERA standing, benchmark the price against registration data, and negotiate with the builder on your side. Free first consultation.