Home/Localities/Central Chennai/Construction of Stilt Floor + 3 Floors

Construction of Stilt Floor + 3 Floors

TN/29/Building/0118/2020PAST COMMITTED DATE

Construction of Stilt Floor + 3 Floors is registered with TNRERA as TN/29/Building/0118/2020 (Building registration, 2020). The promoter is Thiru. E.VISHAL, Proprietor, M/s. Evergreen Promoters. The RERA-committed completion date is 31 Dec 2023 — that date has now passed. Committed dates are legally binding under RERA.

6 Mar 2020
31 Dec 2023
12
0

Latest quarterly progress filing

Caution: the RERA-committed completion date has passed, and the last quarterly filing reported 70% physical completion. Ask the builder for the current status and updated timeline before paying anything.

70%
75%

Stage, as filed: Block/Tower, Floor wise work completed. Outer white in progress

Source: the project's Quarterly Progress Report filed with TNRERA (as on the quarter shown; may not reflect current status).

About this registration

Construction of Stilt Floor + 3 Floors with 12 dwelling units at Plot No.1/5, Old Door No.109, New Door No.190, Lake View Road, West Mambalam, Chennai – 600033 Comprised in R.S.No.177/2, T.S.No.67, Block No.42 of Kodambakkam Village, Mambalam Taluk, Chennai District.

Approval: Planning Permission issued by the Deputy Planner/APU/CMDA/Egmore/Chennai-8,Vide Lr.No. PP/NHRB/C/554/2019, dated 23.10.2019. Building Permission issued by the Executive Engineer(TP)/Greater Chennai Corporation, Vide Lett

Status on register: Progress of Work as on March 2022

Builder track record: Thiru. E.VISHAL, Proprietor, M/s. Evergreen Promoters

Thiru. E.VISHAL, Proprietor, M/s. Evergreen Promoters has 1 project on the TNRERA register since 2020, with no completion-date extensions on record.

Frequently asked

Is Construction of Stilt Floor + 3 Floors RERA registered?

Yes — registered with TNRERA as TN/29/Building/0118/2020 in 2020. Always quote this number when dealing with the builder; unregistered projects cannot legally be marketed or sold in Tamil Nadu.

When will Construction of Stilt Floor + 3 Floors be completed?

The RERA-committed completion date is 31 Dec 2023. No deadline extensions are on record.

Who is the builder of Construction of Stilt Floor + 3 Floors?

Thiru. E.VISHAL, Proprietor, M/s. Evergreen Promoters.

← All Central Chennai projects and market data

Source documents on TNRERA

These are the government's own filed documents for this project. We link them directly — verify anything on this page against them.

Shortlisting here? Verify before you pay.

We check title and RERA standing, benchmark the price against registration data, and negotiate with the builder on your side. Free first consultation.