Salma

TN/29/Building/0088/2024PAST COMMITTED DATE

Salma is registered with TNRERA as TN/29/Building/0088/2024 (Building registration, 2024). The promoter is 1) M/s. Salma Constructions Private Limited, Rep. by its Director, Thiru. H.Dawood Imran Khan. The RERA-committed completion date is 21 Jun 2026 — that date has now passed. Committed dates are legally binding under RERA.

1 Apr 2024
21 Jun 2026
10
0

Latest quarterly progress filing — Sep 2025

Caution: the RERA-committed completion date has passed, and the last quarterly filing reported 95% physical completion. Ask the builder for the current status and updated timeline before paying anything.

95%
95%

Stage, as filed: Block/Tower, Floor wise One Block Sanitary Fixtures

Source: the project's Quarterly Progress Report filed with TNRERA (as on the quarter shown; may not reflect current status).

About this registration

Project Name: “Salma’s SNKP Illam” - Construction of Registration of Stilt Floor + 5 Floors Residential Building with 10 Dwelling Units (Height - 18.30m) availing Premium FSI at Plot No.97, Old Door No.8, New Door No.13, Saravana Street, T.Nagar, Chennai comprised in T.S.No.6435, Block No.140 of T.Nagar Village within the limit of Greater Chennai Corporation.

Approval: CMDA issued Planning Permission No. OL-PP/NHRB/0232/2023 in Letter No. CMDA/PP/NHRB/C/0089/2023, dated 22.06.2023. The Executive Engineer (T.P), Greater Chennai Corporation issued Building Permission in Letter No. CEBA/W

Status on register: Progress of Work as on September 2025

Builder track record: 1) M/s. Salma Constructions Private Limited, Rep. by its Dir

1) M/s. Salma Constructions Private Limited, Rep. by its Director, Thiru. H.Dawood Imran Khan has 1 project on the TNRERA register since 2024, with no completion-date extensions on record.

Frequently asked

Is Salma RERA registered?

Yes — registered with TNRERA as TN/29/Building/0088/2024 in 2024. Always quote this number when dealing with the builder; unregistered projects cannot legally be marketed or sold in Tamil Nadu.

When will Salma be completed?

The RERA-committed completion date is 21 Jun 2026. No deadline extensions are on record.

Who is the builder of Salma?

1) M/s. Salma Constructions Private Limited, Rep. by its Director, Thiru. H.Dawood Imran Khan.

← All Central Chennai projects and market data

Source documents on TNRERA

These are the government's own filed documents for this project. We link them directly — verify anything on this page against them.

Shortlisting here? Verify before you pay.

We check title and RERA standing, benchmark the price against registration data, and negotiate with the builder on your side. Free first consultation.