Construction of Stilt Floor + 3 Floors
Construction of Stilt Floor + 3 Floors is registered with TNRERA as TN/29/Building/0022/2022 (Building registration, 2022). The promoter is 1) Thiru. S.Vijaya Mohan, who has 2 projects on the TNRERA register. The RERA-committed completion date is 31 May 2023 — that date has now passed. Committed dates are legally binding under RERA.
Latest quarterly progress filing — March 2023
Caution: the RERA-committed completion date has passed, and the last quarterly filing reported 90% physical completion. Ask the builder for the current status and updated timeline before paying anything.
Source: the project's Quarterly Progress Report filed with TNRERA (as on the quarter shown; may not reflect current status).
About this registration
Construction of Stilt Floor + 3 Floors with 12 dwelling units comprised in S.No.76/7B1B of Mugalivakkam Village, Alandur Taluk, Chennai District.
Approval: Planning Permission issued by The Executive Engineer (T.P.) / Greater Chennai Corporation / Chennai vide Letter No. PPA/WDCN12/06419/2021, dated 1/10/2021. Building Permission issued by The Executive Engineer (T.P.) / Gr
Status on register: Progress of Work as on March 2023
Builder track record: 1) Thiru. S.Vijaya Mohan
1) Thiru. S.Vijaya Mohan has 2 projects on the TNRERA register since 2022, with no completion-date extensions on record. See the full record →
Frequently asked
Is Construction of Stilt Floor + 3 Floors RERA registered?
Yes — registered with TNRERA as TN/29/Building/0022/2022 in 2022. Always quote this number when dealing with the builder; unregistered projects cannot legally be marketed or sold in Tamil Nadu.
When will Construction of Stilt Floor + 3 Floors be completed?
The RERA-committed completion date is 31 May 2023. No deadline extensions are on record.
Who is the builder of Construction of Stilt Floor + 3 Floors?
1) Thiru. S.Vijaya Mohan, with 2 projects on the TNRERA register and no completion-date extensions on record.
← All Porur Belt projects and market data
Source documents on TNRERA
These are the government's own filed documents for this project. We link them directly — verify anything on this page against them.
Shortlisting here? Verify before you pay.
We check title and RERA standing, benchmark the price against registration data, and negotiate with the builder on your side. Free first consultation.