TN/29/Building/0018/2023PAST COMMITTED DATE

Krishna is registered with TNRERA as TN/29/Building/0018/2023 (Building registration, 2023). The promoter is 1) M/s. Indu Housing Development (Chennai) Pvt. Ltd., Rep. by its Managing Director, Thiru. S.P.Babuvijay. The RERA-committed completion date is 31 Jul 2025 — that date has now passed. Committed dates are legally binding under RERA.

10 Jan 2023
31 Jul 2025
10
0

Latest quarterly progress filing — March 2024

Stage, as filed: Block/Tower, Floor wise Commenced

Source: the project's Quarterly Progress Report filed with TNRERA (as on the quarter shown; may not reflect current status).

About this registration

Project Name: “Krishna” - Construction of Registration of Stilt Floor + 4 Floors + 5th Floor (Part) Residential Building with 10 dwelling units availing Premium FSI at Block:A-4, G.O.C.H. Colony, 2nd Main Road & 6th Cross Street, Besant Nagar, Chennai – 600090 comprised in T.S.No.8/12, Block No.40 of Urur Village within the limit of Greater Chennai Corporation.

Approval: CMDA issued Planning Permission No. OL-PP/NHRB/0040/2022 in Letter No. PP/NHRB/S/0436/2022, dated 04.11.2022. The Executive Engineer (T.P), Greater Chennai Corporation issued Building Permission No. CEBA/WDCN13/00359/202

Status on register: Progress of Work as on March 2024

Builder track record: 1) M/s. Indu Housing Development (Chennai) Pvt. Ltd., Rep. b

1) M/s. Indu Housing Development (Chennai) Pvt. Ltd., Rep. by its Managing Director, Thiru. S.P.Babuvijay has 1 project on the TNRERA register since 2023, with no completion-date extensions on record.

Frequently asked

Is Krishna RERA registered?

Yes — registered with TNRERA as TN/29/Building/0018/2023 in 2023. Always quote this number when dealing with the builder; unregistered projects cannot legally be marketed or sold in Tamil Nadu.

When will Krishna be completed?

The RERA-committed completion date is 31 Jul 2025. No deadline extensions are on record.

Who is the builder of Krishna?

1) M/s. Indu Housing Development (Chennai) Pvt. Ltd., Rep. by its Managing Director, Thiru. S.P.Babuvijay.

← All Central Chennai projects and market data

Source documents on TNRERA

These are the government's own filed documents for this project. We link them directly — verify anything on this page against them.

Shortlisting here? Verify before you pay.

We check title and RERA standing, benchmark the price against registration data, and negotiate with the builder on your side. Free first consultation.